ORIGINAL RESEARCH article

Front. Public Health, 02 February 2024
Sec. Occupational Health and Safety

Safety risk assessment of subway shield construction under-crossing a river using CFA and FER

\r\nKuang HeKuang He1Tianlin CuiTianlin Cui2Jianhua ChengJianhua Cheng3Yanlong Huang
Yanlong Huang3*Hujun LiHujun Li3Huihua ChenHuihua Chen4Ke YangKe Yang3
  • 1Southwest Jiaotong University Rail Transit Transportation System National Primary Laboratory, Chengdu, Sichuan, China
  • 2Zhengzhou Metro Group Co. Ltd., Zhengzhou, Henan, China
  • 3Department of Civil Engineering, Henan Polytechnic University, Jiaozuo, Henan, China
  • 4Department of Civil Engineering, Central South University, Changsha, Hunan, China

Numerous subway projects are planned by China's city governments, and more subways can hardly avoid under-crossing rivers. While often being located in complex natural and social environments, subway shield construction under-crossing a river (SSCUR) is more susceptible to safety accidents, causing substantial casualties, and monetary losses. Therefore, there is an urgent need to investigate safety risks during SSCUR. The paper identified the safety risks during SSCUR by using a literature review and experts' evaluation, proposed a new safety risk assessment model by integrating confirmatory factor analysis (CFA) and fuzzy evidence reasoning (FER), and then selected a project to validate the feasibility of the proposed model. Research results show that (a) a safety risk list of SSCUR was identified, including 5 first-level safety risks and 38 second-level safety risks; (b) the proposed safety risk assessment model can be used to assess the safety risk of SSCUR; (c) safety inspection, safety organization and duty, quicksand layer, and high-pressure phreatic water were the high-level risks, and the onsite total safety risk was at the medium level; (d) management-type safety risks, environment-type safety risks, and personnel-type safety risks have higher expected utility values, and manager-type safety risks were expected have higher risk-utility values when compared to worker-type safety risks. The research can enrich the theoretical knowledge of SSCUR safety risk assessment and provide references to safety managers for conducting scientific and effective safety management on the construction site when a subway crosses under a river.

1 Introduction

China, being the world's second-largest economy, is rushing toward becoming an urbanized and industrialized country (1). The government has gradually enacted laws and increased investment to facilitate infrastructure construction, to create jobs, and improve their people's living standards (24). The subway, as a typical city infrastructure characterized by high traffic efficiency, safety, stability, and energy-saving, is often found on the city planners' desks (5, 6). The city is a highly complex human settlement system, often with roads, rails, and rivers running through it. Thus, subway construction can hardly avoid crossing a river. Although most of the subway project contractors select shield construction as the tunneling technique considering its high safety and low impact, the construction process is often susceptible to safety accidents (79) (e.g., gushing water, collapse) when under-crossing a river because of the complex geological and hydrological environment. These safety accidents often cause substantial casualties and monetary losses (10, 11). For instance, a gushing water accident occurred when Foshan subway line 2 crossed under a river, causing 12 deaths, 8 injuries, and a wide-range road collapse (12). Therefore, there is an urgent need to investigate the safety risks of subway shield construction under-crossing a river (SSCUR).

Large scale studies have been conducted on shield construction safety risk, and their research mainly focused on safety risk identification and safety risk assessment. Regarding safety risk identification, previous scholars have identified shield construction safety risks from different perspectives. For example, Pan et al. (13) followed the framework of “personnel-machine-material-method-environment,” and identified personnel-type, machine-type, environment-type, and management-type safety risks during shield construction; Liu et al. (14) found out the shield construction safety risks by using a questionnaire survey, including tunnel excavation, shield machine launch, segment assembly, special procedures and conditions, shield machine arrival, grouting, lead excavation, slag removal, and shaft construction. As for safety risk assessment, previous researchers often used the analytic hierarchy process (15), cloud model (15), fault tree analysis (16), Bayesian network (17, 18), and backpropagation (BP) neural network (1921) as assessment techniques. For example, Chung et al. (22) applied a Bayesian network model to evaluate safety risks during tunnel shield construction. A comprehensive analysis of the existing literature found that most studies investigated the shield construction safety risks in construction under-crossing complex geological conditions, and in construction under-crossing existing buildings and pipelines, except for Wu and Zou (21), combined entropy weight method and cloud model to evaluate the static risk of underwater shield tunnel construction. However, only natural environment-type, tunnel-type, and management-type safety risks were discussed in Wu and Zou's study, and the safety risks related to personnel and method, although very important, had not been taken into account. Consequently, the existing safety risk list is incomplete for evaluating the safety risk during SSCUR. Besides, the evaluation approaches mentioned above mainly rely on a small amount of expert data. Thus, how to incorporate more expert data into the evaluation process to obtain more objective risk assessments is also a question that needs further exploration.

To fill the research gaps, the paper examines the safety risk assessment of SSCUR. The main purposes of this study are to: (1) provide a systematic and feasible safety risk list for SSCUR based on literature analysis and experts' evaluation; (2) propose a quantitative method to assess the safety risks of SSCUR; (3) select a case to validate the proposed quantitative approach. The research can enrich the theoretical knowledge of SSCUR safety risk assessment and provide references to safety managers for conducting scientific and effective safety management on the construction site when a subway crosses under a river.

2 Literature review

At present, more subway tunnels choose shield construction techniques with the development of shield machine manufacturing technology, because this tunneling technique is characterized by more safety, less environmental impact, and a higher automation level (6, 7). Subway tunnels are generally planned underground; thus, subway tunnel construction often encounters various complex environmental contexts (e.g., under-crossing complex overburden layers, adjacent to rivers, existing pipelines, and tunnels). Previous studies have investigated the shield construction safety risks in some complicated settings, including construction under-crossing the complex overburden layer (6, 23, 24), construction under-crossing existing buildings (2527), construction under-crossing existing tunnels (28, 29), construction under-crossing existing pipelines (30), and construction adjacent to a bridge (31). The topics of these studies are mainly focused on two aspects, i.e., safety risk identification and safety risk assessment.

2.1 Safety risk identification of subway shield construction

Safety risk identification is the prerequisite of the safety risk assessment. The existing literature, project cases, accident reports, and industry standards were often selected as texts for extracting the safety risks, but the previous scholar might select different frameworks to identify safety risks (27, 30). Some scholars used the framework of “machine-environment-management” (Framework 1) (23, 24, 29, 31), and they divided the identified second-level safety risks into machine-type, environment-type, and management-type safety risks. Machine-type safety risks refer to the safety risks arising from machine failure or misoperation; environment-type safety risks refer to the safety risks arising from poor geological and hydrologic conditions; and management-type safety risks focus on the organization or management aspects (e.g., technique arrangements, team or organization management). For instance, Hu et al. (23) used this framework to investigate the subway shield construction safety risks when under-crossing soft overburden layers, and identified geological complex conditions, underground water conditions, the minimum thickness of the overburden layer, the minimum radius of curvature, construction speed, distance from the surrounding environment, and construction management level as second-level safety risks; Zhai et al. (31) applied this view to examine the subway shield construction safety risks when being adjacent to an existing bridge and summed up the relevant second-level safety risks, involving geological and hydrological condition, shield construction parameters, tunnel conditions, bridge conditions, and organization and management risks. Some other scholars argued the subway shield construction is a complex system, and the “personnel-machine-environment” system was important when tackling this type of complex system problem, thus they used the framework of “personnel-machine-environment” (Framework 2). Compared to Framework 1, this framework incorporates the management-type safety risks into environment-type safety risks and highlights personnel's roles in safety risk controlling. Besides, the personnel-type safety risks are only related to the individual participating in construction and were further subdivided into worker-type safety risks and manager-type safety risks (5, 6). For example, Chen et al. (5) and Liu et al. (6) used this framework to examine subway shield construction safety risks when under-crossing complex overburden layers, subdivided environment-type safety risks into natural environment safety risks, manmade environment safety risks, management environment safety risks, and working environment safety risks, and identified 35 relevant second-level safety risks. Other scholars slightly modified Framework 2, they sorted out the management-type safety risks from the environment-type safety risks like Framework 1 and formed the framework of “personnel-machine-environment-management” (Framework 3). For instance, Pan et al. (13) and Wu et al. (32) utilized this framework to investigate the shield construction safety risks respectively. Pan et al.'s research identified 12 second-level safety risks, and Wu et al.'s study listed 15 second-level safety risks. Besides, there exists an all-inclusive framework, i.e., the “personnel-machine-material-method-environment” framework (Framework 4). Compared to the three frameworks mentioned earlier, this framework adds material-type and method-type safety risks. Material-type safety risks refer to the safety risks that arise from raw materials, components, semi-finished products, and finished products during construction (e.g., broken pipe segments, unqualified grouting materials); Method-type safety risks mainly focus on the construction technology aspects (e.g., shield tunneling technology and grouting technology). Li et al. (33) and Fan and Wang (34) examined the subway shield construction safety risk and collected the safety risks based on the framework. Above all, the four frameworks mentioned earlier were aligned with the total quality management theory of “man-machine-material-method-environment.” The differences between these four frameworks stem from the degree of the previous scholars' attention to these different aspects. The four frameworks provide the theoretical or literature basis for the identification framework applied in the study.

2.2 Safety risk assessment of subway shield construction

Literature on safety risk assessment focused on designing safety risk assessment models. The safety risk assessment model describes the calculation process of the risk assessment. As there exist multiple safety risks in the index framework, the two key questions in designing the assessment model are the weight-determining method and the safety risk measurement. As for the weight-determining method, earlier research selected the analytic hierarchy process (AHP) to determine the weight system. For instance, Li et al. (33) selected AHP to calculate the weights of safety risks when investigating the safety risks in slurry balancing shield construction. Gradually, some more objective techniques were introduced to mitigate the subjectivity in determining the weights. For instance, Fan and Wang (34) applied ISM-DEMATEL and Shapley value method to determine weights of safety risks to consider the relationships between different safety risks; Zhai et al. (31) selected a combinatorial weighting method by integrating G1 and CRITIC on shield construction safety risk when being adjacent to an existing bridge.

As for the safety risk measurement, previous literature can identify many quantitative methods. The fuzzy comprehensive evaluation method is widely applied in the evaluation of shield construction safety risks (33, 35). For instance, Ren et al. (35) chose this method to assess the total shield construction safety risks when being adjacent to an existing building. The matter-element method is another widely used technique (25, 34). This technique has advantages in determining the risk rating by connecting the risk and its risk criteria (4). At present, the Bayesian network (29, 36), cloud model (24, 32), and evidence reasoning theory (29) were also introduced into the area of safety risks to decrease the impact of uncertainty. Wu et al. (29) integrated fuzzy Bayesian and evidence theory to evaluate the subway shield construction safety risk when under-crossing an existing tunnel; Wu et al. (32) chose the cloud model to evaluate the shield construction safety risks; further, Chen et al. (24) applied the extension cloud theory and optimal cloud entropy to examine the shield construction safety risk when being adjacent to an existing building. Besides, Monte Carlo (31) and Systematic dynamic (SD) (13) were also applied to the shield construction safety risk assessment by simulating the probability sampling process and the dynamic relationships between different safety risks.

The above studies showed that an evaluation approach including a weight-determining method and safety risk measurement method was needed for a multifactor evaluation framework. For the weight-determining method, the key to the method selection is to mitigate the subjectivity caused by fewer experts. Confirmatory factor analysis (CFA) is an effective relationship extraction method based on more data collected by questionnaire (32); thus, the method can significantly reduce the impact of subjective judgment caused by a small number of experts. Therefore, this study applied the CFA to determine the weights of safety risks. Besides, evidence reasoning theory is a useful approach to integrate more information and reduce uncertainty (29), thus we selected fuzzy evidence reasoning to measure the value of a single safety risk and the onsite overall safety risk.

3 Safety risk identification of SSCUR

3.1 The framework for safety risk identification

Although few studies investigated the safety risks during SSCUR, the frameworks identified in the previous literature can provide feasible frameworks to identify the safety risks. As explained earlier, Framework 3 and Framework 4 are more methodical frameworks. First, Framework 3 does not include material-type safety risks when compared to Framework 4. The reason is that there might be duplication in safety risk statistics in Framework 4, namely, non-standard materials cannot be used in the construction after multiple rounds of material inspections, while the material damage of the final-finished production is mostly caused by the non-standard construction operations, which are analyzed in personnel-type, machine-type, and method-type safety risks (32, 34). Second, Framework 3 distinguishes management-type safety risk from environment-type safety risk. The two are different. Management-type safety risks arise more from organization-level non-compliant behaviors. However, Framework 4 incorporates the method-type safety risk in its analysis views. Therefore, we adjusted Framework 3 based on Framework 4 and proposed the safety risk identification framework for SSCUR. The identification framework is presented in Figure 1. It is noted that personnel-type safety risks arise from inappropriate physical, psychological, and ability conditions, and non-compliant behaviors at the individual level; and the personnel include workers and managers.

Figure 1
www.frontiersin.org

Figure 1. Safety risk identification framework of SSCUR.

3.2 The process for safety risk identification

Based on the aforementioned safety risk identification framework, the paper applied a two-step approach to collect the safety risks of SSCUR. First, we used a literature review to identify the related safety risks. Second, we arranged an expert group to evaluate and enrich the pre-identified safety risks.

Step 1. Safety risk identification based on literature review.

We selected CNKI and Scopus as retrieval databases and the searching strategy is ((“safety” OR “risk*”) AND “shield construction”) OR [“shield construction” AND “river*” AND (“safety” OR “river”)]. We also limited the type of literature to articles and reviews. The search shows 84 English articles and 75 Chinese articles. The researchers selected the final relevant studies by reading titles, abstracts, and texts. Two selection criteria were used to determine the relevance to the research, including: (a) removing the studies which are unrelated to shield construction, for example, the term “shield construction” and “safety” are all in the abstract of Yang et al.'s study (37), but this research is focused on the on-site shield spoil utilization; (b) removing the studies which are unrelated to shield construction safety or shield construction risks, for instance, Dai et al.'s (38) paper mentioned “shield construction” and “safety,” but the research is about the attitude and position prediction of shield machine in tunneling. After the exclusion process, 54 articles were retained, including 31 English articles and 23 Chinese articles. Safety risks were initially extracted from the retained articles based on the identification framework mentioned earlier. The preliminary safety risk list (including first-level safety risk categories and second-level safety risks) is presented in Appendix A.

Step 2. Safety risk evaluation and enrichment based on experts' group evaluation.

Twenty safety management experts were invited to evaluate the safety risk list gained in the previous step (see Appendix A). The invited 20 experts all have at least 5 years of construction experience in shield construction, and they include 2 professor-level experts, 5 senior engineers, and 13 site engineers. The experts were asked to mark whether the safety risks in the list were important or not and to propose any improvements to the safety risk list. If more than 10 experts marked the safety risk, then the safety risk was retained in the list. Based on the statistics on the experts' marks, safety control, failure of soil transport vehicle, safety management system, and high underground water were removed from the safety risk list. Besides, 5 experts were suggesting that incorporate safety skills and safety experience into safety competency. After the above-mentioned amendment, the final safety risk list of SSCUR was presented in Table 1.

Table 1
www.frontiersin.org

Table 1. Safety risk list of SSCUR.

4 Safety risk assessment model for SSCUR

We designed a safety risk assessment model for SSCUR. The assessment model integrated the confirmatory factor analysis (CFA) (39, 40) and the fuzzy evidence reasoning (FER) (41, 42). The CFA method was utilized to determine the weights of the safety risks, and the FER method was applied to measure the single safety risk or the onsite total safety risk.

4.1 Weights calculation based on CFA

Confirmatory factor analysis (CFA) is a widely used data analysis method belonging to factor analysis. Compared to the exploratory factor analysis, which is used to find out the common factor structure from the messy data, CFA aims at validating the feasibility of pre-identified common factor structure (i.e., dimension structure) (43, 44).

A questionnaire survey was chosen to collect data for further CFA (45). The questionnaire is presented in Appendix B. The questionnaire survey was conducted by using the Wenjuanxing platform (46) and the compiled online questionnaire was sent to onsite managers who have cooperation relationships with the researchers. A total of 232 questionnaires were distributed and 197 responses were retained after the validity test. The demographic information of 197 respondents was presented in Appendix C.

The retained data were first imported into SPSS 23 to test the reliability (47, 48). Cronbach's alpha was 0.942 (49), indicating the collected data have high internal consistency and reliability. Bartlett's test of sphericity produced a significant p-value (p < 0.001), showing that the data follow the normal distributions (50). The value of KMO was 0.921, suggesting the high correlations between the items and good sampling adequacy for factor analysis (39, 51).

Then, the collected data were imported into AMOS 23 to conduct a CFA (52, 53). The concept model was constructed based on the safety risk framework and it was presented in Figure 2. CFA shows a better fit (χ2/df = 2.33 < 3; CFI = 0.903) and the standard path coefficients can be gained, which are shown in Table 2. The standard path coefficients denote the relationship strength between different variables (5457), namely the second-level safety risks and their first-level safety risk. Thus, based on the standard path coefficients, we calculated the weights of the safety risks, which are shown in Table 3.

Figure 2
www.frontiersin.org

Figure 2. Safety risk identification framework of SSCUR.

Table 2
www.frontiersin.org

Table 2. Standard path coefficients of the CFA.

Table 3
www.frontiersin.org

Table 3. Standardized weights of the safety risks.

4.2 Safety risk measure based on FER

The FER algorithm includes the follow-up five steps.

Step 1. Using triangular fuzzy numbers to represent safety risks.

Safety risk R can be expressed as R = P × S, that is, the production of the occurrence probability of a safety risk P and the consequence severity of a safety risk S. Due to the influence of uncertain factors, it is often difficult to measure the safety risks quantitatively. A practical and effective approach is to apply qualitative descriptions to represent safety risk grades (41). The occurrence probability of a safety risk can be qualitatively expressed on a verbal scale as “extremely low,” “low,” “relatively high,” “high,” and “extremely high.” The consequence severity can also be described as “no impact,” “minor,” “large,” “dangerous,” and “catastrophic.” In this paper, the verbal assessment grade descriptions of P and S are transformed into triangular fuzzy numbers, and the corresponding relationships were shown in Table 4.

Table 4
www.frontiersin.org

Table 4. Corresponding relationships between verbal assessment grades and the triangular fuzzy numbers.

Assuming that the occurrence probability P and the consequence severity S are represented by triangular fuzzy numbers, i.e., P~=(lP,mP,uP), S~=(lS,mS,uS), then the value of the corresponding safety risk is also a triangular fuzzy number, which can be represented by Equation 1 (58, 59).

R~=(lPlS,mPmS,uPuS)    (1)

Step 2. Constructing the fuzzy confidence structure model for the safety risks assessment grades.

Assuming that there exist N assessment grades for each safety risk and the corresponding membership functions are known, thus we can establish the fuzzy confidence structure of the safety risk assessment grades, which is presented by Equation 2.

FBS(R)={(FHn,βn),n=1,2,3,,N}    (2)

In the Equation 2, FHn denotes the fuzzy assessment grades; N denotes the numbers of the assessment grades; βn denotes the confidence level of R at fuzzy assessment grades, besides, βn ≥ 0 and n=1Nβn 1.

In this article, we assumed that there exist five assessment grades for a safety risk and the corresponding membership functions adopted fuzzy triangular numbers. The definition and description of the safety risks grades are presented in Table 5. As such, the fuzzy confidence structure of the safety risks assessment grades can be expressed by Equation 3 and the membership functions of the 5 assessment grades are depicted in Figure 3.

FBS(R)={(FHn,βn),n=1,2,3,4,5}    (3)

Step 3. Calculating the confidence level of each safety risk.

Table 5
www.frontiersin.org

Table 5. Definition of safety risk assessment grades and their membership functions.

Figure 3
www.frontiersin.org

Figure 3. The membership functions of the 5 assessment grades.

Through this step, we can calculate the confidence structure of each safety risk (βn) based on the triangular fuzzy values of each safety risk (R~). The calculating method includes the four rules below.

(1) Draw the membership curve based on R~;

(2) Find out the intersection points between the membership curve of R~ and the five safety risk grade membership curves in Figure 3, and calculate the corresponding ordinate of each intersection point (i.e., confidence value of the corresponding assessment grades). If there exist no intersection points, the confidence value on this level is zero.

(3) If there exist 2 intersection points between the membership curve of R~ and the five-grade membership curves, the larger ordinate will be used as confidence value;

(4) Sequentially determine the confidence values of a safety risk at the 5 assessment grades, and then standardize the five confidence values. As such the confidence structure of a safety risk Z(R) can be gained, which is expressed by Equation (4).

Z(R)={βEL,βL,βM,βH,βEH}    (4)

Step 4. Calculating onsite total safety risk based on evidence reasoning.

Assuming that there exists a risk assessment problem RE with L risk indexes ri (i = 1, 2, …, L), the weights of these indexes ri are ωi, and every risk index follows the fuzzy confidential (Equation 8) (60).

min=ωiβin,n=1,2,3,,N;i=1,2,3,,L    (5)
miH=1-n=1Nmin,i=1,2,3,,L    (6)
m¯iH=1-ωi,i=1,2,3,,L    (7)
m~iH=ωi(1-n=1Nβin),i=1,2,3,,L    (8)

In the above Equations, min denotes the basic fuzzy confidence value of risk index ri at the fuzzy risk level of FHn, miH denotes the uncertain risks due to lack of information, which includes m¯iHand m~iH.

Let mI(i)nrepresents the confidence values to the nth assessment grade of an upper-level risk index which the first I lower-level indexes support; and mI(i)H represents the retained probability after all the first i lower-level risk indexes are assigned to all the assessment grades, thus the recursive Equations of mI(i)n and mI(i)H can be presented in Equations 912 (60, 61).

mI(i+1)n=KI(i+1)(mI(i)nmi+1n+mI(i)nmi+1H+mI(i)Hmi+1n    (9)
m~I(i+1)n=KI(i+1)(m~I(i)Hm~i+1H+m~I(i)Hm¯i+1H+m¯I(i)Hm~i+1H    (10)
m¯I(i+1)n=KI(i+1)(m¯I(i)Hm¯i+1H    (11)
KI(i+1)=(1n=1Nt=1tnNmI(i)nmi+1t1,i=1,2,3,,L1    (12)

Then, the fuzzy confidence values of an upper-level risk index βn can be gained based on Equation 13.

βn=mI(L)n1-m¯I(L)H,n=1,2,3,,N    (13)

Based on the aforementioned processes, we can calculate the fuzzy confidence values of all the second-level safety risks and the onsite total safety risks.

Step 5. Calculating the expected utility values of the safety risks.

Let u(Hn) represent the expected utility values of the different safety risk grades, then the total expected utility value of safety risks can be gained based on Equation 14 (59).

u(R)=n=1Nβnu(Hn)    (14)

In Equation 14, u(Hn)=n5,n=1,2,3,N.

Step 6. Determining the grades of the safety risks.

If the total expected utility value u(R) ∈, n = 1, 2, 3, ⋯ , N, then the safety risk grade is n.

5 Case validation

5.1 Project overview

The subway interval between Xizhou Station and South Huanghe Road Station of Zhengzhou Subway line 12 crossed under the Qili River at K12 + 180~K12 + 270. The right line crosses under the Qili River approximately orthogonally, and the left line crosses under the Qili River at an angle of 80°. Currently, the cross-section of the Qili River is a compound cross-section, with an opening width of about 90m and a bottom width of about 50m. Two levels of slope protection are provided on both banks, with a main channel slope of 1:3 and an embankment slope of 1:3. The slope height is 6.4–7.0m. The river bottom is protected by dry masonry, while the first level slope is protected by a C20 concrete slab. The minimum vertical clear distance between the tunnel arch and the river bottom is approximately 18.2m. The section under-crossing is located in the quicksand layer and the underground water is located above the tunnel top.

5.2 Identify and assess the safety risks of the project based on experts' group evaluation

The tunnel section under-crossing the Qili River is a highly risky section of the subway interval between Xizhou Station and South Huanghe Road Station. Before under-crossing the Qili River, the project management department invited an experts' group with 15 experts. These experts are from the expert team mentioned earlier (20 safety management experts selected for evaluating safety risks in Section 3.2) and they include 1 professor-level expert, 5 senior engineers, and 9 site engineers. The experts were asked to identify the safety risks while under-crossing the Qili River and then evaluate the occurrence probability and consequence severity of the identified safety risks.

After the onsite investigation, the experts analyzed the project documents and inquired about some project issues from the project managers. Then, a separate safety risk checklist (see Appendix D) was distributed to every expert. The safety risk checklist covers all the pre-identified safety risks in Table 1. The experts marked the safety risks they consider significant and the corresponding occurrence probability and consequence severity of these safety risks. Onsite management personnel collected all the checklists and calculated marked frequency, occurrence probability, and consequence severity of the second-level safety risks. If the marked frequency of a second-level safety risk is less than five, the second-level safety risk is removed. The level of the occurrence probability and consequence severity of a second-level safety risk were determined by the levels selected by most experts. According to the calculation, the selected safety risks by the experts' group were presented in Table 6, and the grades of the occurrence probability and consequence severity of the safety risks were presented in Table 7.

Table 6
www.frontiersin.org

Table 6. The identified safety risks by the experts.

Table 7
www.frontiersin.org

Table 7. The levels of occurrence probability and consequence severity of the safety risks based on the experts.

5.3 Calculate the values of safety risks based on CFA and ER

According to the transformation rule (see Table 4), the triangular fuzzy numbers of the safety risks can be calculated and the results are presented in Table 8. Following the transformation rules in step 3, we computed the confidence structure of the second-level safety risks, and the results are shown in Table 9.

Table 8
www.frontiersin.org

Table 8. The triangular fuzzy values of the safety risks.

Table 9
www.frontiersin.org

Table 9. The confidence structure of the safety risks.

Then the confidence structure of the first-level safety risks and the onsite total safety risk can be calculated by using Equations 514. The results are shown in Table 10.

Table 10
www.frontiersin.org

Table 10. The confidence structure of the first-level safety risks and the total onsite safety risk.

We determined the risk grades of the safety risks by using Equation 14, and the results were presented in Table 11.

Table 11
www.frontiersin.org

Table 11. The risk grades of all the safety risks.

As can be seen in Table 11, safety inspection (M5), safety organization & duty, quicksand layer (MN3), and high-pressure phreatic water (HE1) are at the high grade, which shows that these safety risks are more likely to cause safety accidents during shield construction. Thus, the onsite manager should develop a special construction plan in advance to identify and prevent these safety risks. Most of the safety risks are medium-grade risks and the results indicate that some common safety countermeasures should be taken to address these safety risks.

As for the different first-level safety risks, although they are all at the medium grade, the management-type safety risks have the maximum expected utility value, the environment-type safety risks, the personnel-type safety risks, and the method-type safety risks follow closely behind, and the machine-type safety risks have the minimum expected utility value. It indicates that non-standard management is still the most important factor causing safety accidents in China. Onsite managers should focus on the control of management-type, environment-type, and personnel-type safety risks. Besides, when compared to worker-type safety risks, manager-type safety risks have higher expected utility values, which indicates that managers are the core of safety risks. The design of safety institutions and management regulations should consider how to improve managers' safety management competency and how to motivate the managers' behavior intentions.

The total onsite safety risk is at the medium grade, which indicates that overall, the safety risk is at an average level. It also can be inferred that the project management department has an average level of management competency on safety risks during SSCUR. More safety experiences should be collected and more safety training should be carried out so that its manager can quickly and gradually improve control and emergency ability on shield construction safety risks.

6 Discussion and management implication

The article proposes a safety risk list of SSCUR, and the list includes five first-level safety risks and 38 second-level safety risks. This is the theoretical innovation of this study. The identified first-level safety risks are personnel-type, machine-type, method-type management-type, and environment-type safety risks, and the second-level safety risks were identified based on a literature review and expert interview. Compared to the prior studies, we identified more safety risks of subway shield construction when under-crossing a river. For instance, Chan et al. (62) investigated the very large tunnel safety risk across the Qiantang River, and identified machine-type, operation-type, and environment-type safety risks, but neglected the personnel-type and management-type safety risks. Some technique-focused papers only analyzed safety technology problems and the corresponding safety countermeasures when a subway crosses under a river (6367). Thus, the safety risk list identified in this paper is more systematic and completed. It involves almost all subway construction safety risks when under-crossing a river, and has a stronger generalization ability, which can guide the shield construction practice when under-crossing a river.

This article proposed a new integrated approach to evaluate shield construction safety risk by integrating confirmatory factor analysis (CFA) and fuzzy evidence reasoning (FER). This is the method innovation of this study. CFA or SEM-kind methods have been introduced into safety risk assessment in the existing literature (68, 69), these methods can calculate the relationship degrees between some low-level variables (e.g., second-level safety risks) and an upper-level latent variable (e.g., first-level safety risk), and provide an approach for determining weights (56, 70). The advantages of these methods are that they make the weights of variables more objective by statistically analyzing large-scale questionnaire data. FER is also a widely used analytic technique in safety risk analysis (71, 72). This technique can partially resolve the semantic vagueness and uncertainty caused by an expert's evaluation and fuse multiple pieces of evidence to gain a comprehensive evidential inference (71, 73). Thus, compared to other evaluation models in shield construction safety risk, for instance, AHP, and FCE, the new proposed assessment model can gain more scientific and accurate results, which can provide a more precise foundation for safety risk prevention and controlling.

The proposed CFA-FER model was applied to a case, i.e., Zhengzhou subway line 12 under-crossing the Qili River, to test its feasibility. The calculation processes and results validate the proposed method can assess single safety risk and onsite total safety risk during shield construction under-crossing a river. The calculation results show that management-type safety risks have the maximum expected utility value. This finding is consistent with the prior literature and the actual situation in China. For instance, Zhang et al. (74) pointed out that management-type reasons are the most important ones causing safety accidents in China, non-standard safety management is still a common phenomenon in most project sites (75, 76). Besides, manager-type safety risk has a larger expected utility value than worker-type safety risk. This finding also can be explained based on prior research. As the core of the classic two-agent management model, the safety manager plays a leading role in safety management (77, 78). The workers' low safety awareness and high-frequency unsafe behaviors mainly derived from managers' negligence and the failure of the safety management system (9, 79, 80). Environment-type safety risks have relatively larger expected utility value, especially, the high-pressure phreatic water is the high-level safety risk. Previous literature has highlighted the significance of the hydrological environment for shield construction, and surface water and groundwater have been proven to be the direct causes of safety accidents such as excavation face collapse, water gushing, and even tunnel flooding (81, 82).

Based on the above-mentioned analysis, some management policies can be suggested for better on-site safety management. Firstly, management-type safety risks and manager-type safety risks were assessed to be the relatively higher safety risks. Senior and front-line managers can take the follow-up measures: (a) take China's indigenous management context and engineering reality into consideration when formulating management regulations; (b) establish a strict reward and punishment system, improve safety management systems, define managers' responsibilities and obligations, and strengthen the supervision of the construction process; (c) prioritize safety objective even if there are conflicts with schedule and cost objectives, and pay more efforts on the cultivation of high-level safety management personnel. Underground water and overburdened soil layers are the salient safety risks when shield construction crosses under a river. Some measures can also be conducted beforehand to mitigate the negative effect. Project managers can (a) further carry out in-depth geological and hydrological surveys; (b) grout in advance to reinforce the rich-water soil layer and ensure its stability before under-crossing; (c) control excavation speed and continuously monitor the water seepage of the tunnel.

7 Conclusion

The paper used a literature review and an expert interview to identify the safety risks of subway shield construction under-crossing a river, proposed a new safety risk assessment model by integrating CFA and FER, and employed a case to validate the feasibility of the proposed approach. The research conclusions are as follows:

(1) A practice-feasible safety risk list of shield construction under-crossing a river is identified, including 5 first-level safety risks and 38 second-level safety risks. The first-level safety risks include personnel-type, machine-type, method-type, environment-type, and management-type safety risks.

(2) An integrating safety risks assessment model was proposed to quantitatively assess the single safety risk and onsite total safety risk, and the model was validated feasible by applying it to a tunnel section of Zhengzhou subway line 12.

(3) A case study showed that safety inspection, safety organization and duty, quicksand layer, and high-pressure phreatic water were the high-level risks, the onsite total safety risk was at the medium level, and management-type safety risks, environment-type safety risks, and personnel-type safety risks have higher expected utility values. Besides, compared to worker-type safety risks, manager-type safety risks were expected to have higher risk-utility values.

(4) The paper only examined the safety risk assessment SSCUR by providing a safety risk list and an assessment approach. We did not analyze the correlation, causality, and coupling among safety risks, and examine how these safety risks cause safety accidents by mutual interaction. Follow-up studies can further investigate these questions.

Data availability statement

The raw data supporting the conclusions of this article will be made available by the authors, without undue reservation.

Ethics statement

Ethical review and approval was not required for the study on human participants in accordance with the local legislation and institutional requirements. Written informed consent from the participants was not required to participate in this study in accordance with the national legislation and the institutional requirements.

Author contributions

KH: Conceptualization, Formal analysis, Writing – review & editing. TC: Investigation, Writing – original draft. JC: Project administration, Writing – review & editing. YH: Methodology, Writing – review & editing. HL: Validation, Writing – review & editing. HC: Validation, Writing – review & editing. KY: Resources, Writing – review & editing.

Funding

The author(s) declare financial support was received for the research, authorship, and/or publication of this article. This research was funded by the National Natural Science Foundation of China (grant Nos. U1810203 and 52178388), the Zhengzhou Metro Group Co. Ltd. (grand No. H22-541), the Fundamental Research Funds for the Universities of Henan Province (grand No. NSFRF230426), and the Doctoral fund of Henan Polytechnic University (grand No. 760707/038).

Acknowledgments

The research would like to thank Henan Polytechnic University for providing research facilities.

Conflict of interest

TC was employed by Zhengzhou Metro Group Co. Ltd.

The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Publisher's note

All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article, or claim that may be made by its manufacturer, is not guaranteed or endorsed by the publisher.

Supplementary material

The Supplementary Material for this article can be found online at: https://www.frontiersin.org/articles/10.3389/fpubh.2024.1279642/full#supplementary-material

References

1. Cheng J, Yang X, Wang H, Li H, Lin X, Guo Y. Evaluation of the emergency capability of subway shield construction based on cloud model. Sustainability. (2022) 14:13309. doi: 10.3390/su142013309

Crossref Full Text | Google Scholar

2. Zhang C, Qiao M, Li H, Chen H, Yang Z, A. review on blockchain applications in the construction area. J Railway Sci Eng. (2023) 20:1105–15.

Google Scholar

3. Hu X, Zhang X, Dong L, Li H, He Z, Chen H. Carbon emission factors identification and measurement model construction for railway construction projects. Int J Environ Res Public Health. (2022) 19:11379. doi: 10.3390/ijerph191811379

PubMed Abstract | Crossref Full Text | Google Scholar

4. Chen H, Li H, Wang Y, Cheng B, A. comprehensive assessment approach for water-soil environmental risk during railway construction in the ecologically fragile region based on ahp and mea. Sustainability. (2020) 12:7910. doi: 10.3390/su12197910

Crossref Full Text | Google Scholar

5. Chen H, Li H, Hu X. Safety influential factors and accident causation model of subway shield construction. J Railway Eng Soc. (2020) 37:87–97.

Google Scholar

6. Liu T, Chen H, Li H. Research on safety impact factors and safety accident causation mechanism of subway shield construction in mix-ground. J Railway Sci Eng. (2020) 17:266–72.

Google Scholar

7. Li H, Chen H, Cheng B, Hu X, Cai X. Study on formation model of subway construction safety climate based on fuzzy Ism-Dematel. J Railway Sci Eng. (2021) 18:2200–8.

Google Scholar

8. Li H, Chen H, Zhao Z, Hu X, Cheng B, Huang J. Tunnel construction workers' cognitive biases and unsafe behaviors: The mediating effects of risk perceptions. Adv Civil Eng. (2020) 2020:8873113. doi: 10.1155/2020/8873113

Crossref Full Text | Google Scholar

9. Chen H, Li H, Goh Y, A. review of construction safety climate: definitions, factors, relationship with safety behavior and research agenda. Saf Sci. (2021) 142:105391. doi: 10.1016/j.ssci.2021.105391

Crossref Full Text | Google Scholar

10. Zhang J, Li H, Cui L. Total loss framework for safety accident in construction enterprise. China Safety Sci J. (2016) 26:151–6.

Google Scholar

11. Zhang J, Shen X, Li H, Luo C. Study on classification system of intangible losses caused by safety accidents in construction enterprises. China Safety Sci J. (2018) 28:160–5.

Google Scholar

12. Province DoEMoG. Investigation report on major accident of “2·7” permeation collapse of phase I project of foshan city transit line 2 in 2018. (2018). Available online at: http://yjgl.gd.gov.cn/gk/zdlyxxgk/sgdcbg/content/post_2511537.html (accessed July 30, 2023).

Google Scholar

13. Pan H, Gou J, Wan Z, Ren C, Chen M, Gou T, et al. Research on coupling degree model of safety risk system for tunnel construction in subway shield zone. Mathem Probl Eng. (2019) 2019:5783938. doi: 10.1155/2019/5783938

Crossref Full Text | Google Scholar

14. Liu W, Zhao T, Zhou W, Tang J. Safety risk factors of metro tunnel construction in china: an integrated study with EFA and sem. Saf Sci. (2018) 105:98–113. doi: 10.1016/j.ssci.2018.01.009

Crossref Full Text | Google Scholar

15. Wang X, Li S, Xu Z, Li X, Lin P, Lin C. An interval risk assessment method and management of water inflow and inrush in course of karst tunnel excavation. Tunnell Undergr Space Technol. (2019) 92:103033. doi: 10.1016/j.tust.2019.103033

Crossref Full Text | Google Scholar

16. Hyun KC, Min S, Choi H, Park J, Lee IM. Risk analysis using fault-tree analysis (FTA) and analytic hierarchy process (AHP) applicable to shield tbm tunnels. Tunnell Undergr Space Technol. (2015) 49:121–9. doi: 10.1016/j.tust.2015.04.007

Crossref Full Text | Google Scholar

17. Wu X, Feng Z, Liu Y, Qin Y, Yang T, Duan J. Enhanced safety prediction of vault settlement in urban tunnels using the pair-copula and bayesian network. Appl Soft Comput. (2023) 132:109711. doi: 10.1016/j.asoc.2022.109711

Crossref Full Text | Google Scholar

18. Liu W, Zhai S, Liu W. Predictive analysis of settlement risk in tunnel construction: a bow-tie-bayesian network approach. Adv Civil Eng. (2019) 2019:2045125. doi: 10.1155/2019/2045125

Crossref Full Text | Google Scholar

19. Li Z, Wang Y, Olgun C, Yang S, Jiao Q, Wang M. Risk assessment of water inrush caused by karst cave in tunnels based on reliability and ga-bp neural network. Geom Natural Hazards Risk. (2020) 11:1212–32. doi: 10.1080/19475705.2020.1785956

Crossref Full Text | Google Scholar

20. Huang L, Yang J, Zhang C, Jiang C, Su B. Prediction and analysis of shield tunneling parameters in underwater karst stratum based on bp neural network. China Civil Eng J. (2020) 53:75–80.

Google Scholar

21. Wu Z, Zou S. A static risk assessment model for underwater shield tunnel construction. Sadhana. (2020) 45:1–13. doi: 10.1007/s12046-020-01370-w

Crossref Full Text | Google Scholar

22. Chung H, Lee I, Jung J, Park J. Bayesian networks-based shield tbm risk management system: methodology development and application. KSCE J Civil Eng. (2019) 23:452–65. doi: 10.1007/s12205-018-0912-y

Crossref Full Text | Google Scholar

23. Hu C, Lu Z, Mei Y, Zhang W, Zhang Y. On the risk evaluation of the metro shield construction in the soft soil condition background with the extension method. J Safety Environ. (2017) 17:21–6.

Google Scholar

24. Chen H, Yang S, Feng Z, Liu Y, Qin Y. Safety evaluation of buildings adjacent to shield construction in karst areas: an improved extension cloud approach. Eng Appl Artif Intell. (2023) 124:106386. doi: 10.1016/j.engappai.2023.106386

Crossref Full Text | Google Scholar

25. Hu C, Zhang W, Lu Z, Mei Y. On the risk evaluation and control method of the shield tunneling under the hazardous buildings and rivers based on the catastrophe-forecasting theory. J Safety Environ. (2017) 17:1221–7.

Google Scholar

26. Wang X. Safety risk assessment of subway tunnel shield construction undercrossing an existing building. Build Struct. (2023) 53:156.

Google Scholar

27. Qian S, Dong J, Li L. Analysis on the safety influence of shield tunnel construction on its above metrostation. China Safety Sci J. (2009) 19:172–6.

Google Scholar

28. Lu X, Zeng S, Zhao Y, Huang M, Ma SK, Zhang Z. Physical model tests and discrete element simulation of shield tunnel face stability in anisotropic granular media. Acta Geotechn. (2020) 15:3017–26. doi: 10.1007/s11440-020-01041-4

Crossref Full Text | Google Scholar

29. Wu X, Liu Q, Chen H, Zeng T, Wang J, Tao W. Preassessment of safety risk of shield tunneling underneath existing tunnel based on fuzzy bayesian networks and evidence theory. Tunnel Constr. (2021) 41:713–20.

Google Scholar

30. Liu C, Su Y. Pipeline deformation laws and safety risk assessments caused by shield construction. J Railway Sci Eng. (2020) 17:2882–91.

Google Scholar

31. Zhai Q, Gu H, Jie F. Safety evaluation of adjacent bridge in shield tunnel construction based on spa method. J Safety Sci Technol. (2021) 17:129–35.

Google Scholar

32. Wu H, Wang J, Wang M. Shield construction safety risk assessment of metro tunnels based on cloud model. In: 2020 International Conference on Urban Engineering and Management Science (ICUEMS). (2020). doi: 10.1109/ICUEMS50872.2020.00128

Crossref Full Text | Google Scholar

33. Li K, Xia H, Huang H, Tang L, Huang J, Li Q, et al. Ahp-fse-based risk assessment and mitigation for slurry balancing shield tunnel construction. J Environ Public Health. (2022) 2022:1666950. doi: 10.1155/2022/1666950

PubMed Abstract | Crossref Full Text | Google Scholar

34. Fan Y, Wang R. Application of matter-element extension method in safety risk assessment of subway shield construction. J Safety Environ. (2023) 23:1779–90.

Google Scholar

35. Ren J, Yang F, Zhu Y. The risk assessment of shield construction under the condition of adjacent buildings in xi'an metro. J Railway Eng Soc. (2016) 33:88–93.

Google Scholar

36. Zhang L, Liu S, Li K, Xu J, Wang S, Li Q, et al. Prediction of shield construction risks in subway tunnelling based on fault tree and bayesian network. Modern Tunnel Technol. (2021) 58:21–55.

Google Scholar

37. Yang F, Cao T, Zhang T, Hu J, Wang X, Ding Z, et al. An implementation framework for on-site shield spoil utilization—a case study of a metro project. Sustainability. (2023) 15:9304. doi: 10.3390/su15129304

Crossref Full Text | Google Scholar

38. Dai Z, Li P, Zhu M, Zhu H, Liu J, Zhai Y, et al. Dynamic prediction for attitude and position of shield machine in tunneling: A hybrid deep learning method considering dual attention. Adv Eng Inform. (2023) 57:102032. doi: 10.1016/j.aei.2023.102032

Crossref Full Text | Google Scholar

39. Li H, Chen H, Zeng X, Hu X, Cheng B, Tang X. Determining the factor structure of construction safety climate in building engineering: a case study in changsha. J Railway Sci Eng. (2021) 18:1935–42.

Google Scholar

40. Xu Y, Li L, Chen H, Cai X, Li H. Research on the influence of supervisor-worker guanxi on construction workers' safety behavior. J Railway Sci Eng. (2022) 2022:1–13.

Google Scholar

41. Wei D, Zhang Y. Fuzzy witness reasoning-based approach to the risk assessment of the deep foundation pit construction. J Safety Environ. (2021) 21:512–20.

Google Scholar

42. He R, Zhang L, Tiong RLK. Flood risk assessment and mitigation for metro stations: an evidential-reasoning-based optimality approach considering uncertainty of subjective parameters. Reliabil Eng Syst Safety. (2023) 238:109453. doi: 10.1016/j.ress.2023.109453

Crossref Full Text | Google Scholar

43. He X. Multivariate Statistic Analysis, 2nd Ed. Beijing, China: China Remin University Press (2008). 415 p.

Google Scholar

44. Johnson RWD. Applied Multivariate Statistical Analysis, 5th Ed. New Jersey, USA: China Remin University Press. (2002).

Google Scholar

45. Brown TA. Confirmatory Factor Analysis for Applied Research, 2nd Ed. New York, USA: The Guilford Press. (2015).

Google Scholar

46. Wenjuanxing. Wenjuanxing Website (2023). Available online at: https://www.wjx.cn/ (accessed July 30, 2023).

Google Scholar

47. Zhang W. Advanced Courses on Spss Statistical Analysis. Beijing, China: Higher Education Press. (2004).

Google Scholar

48. Pallant J. Spss Survival Manual: A Step by Step Guide to Data Analysis Using Ibm Spss, 6th Ed. England, US: Open University Press. (2016).

Google Scholar

49. Xia N, Ding S, Yuan J. The impact of a challenging work environment: do job stressors benefit citizenship behavior of project managers? Int J Project Manage. (2022) 40:205–17. doi: 10.1016/j.ijproman.2022.01.007

Crossref Full Text | Google Scholar

50. Xie Q, Xia N, Yang G. Do family affairs matter? Work–family conflict and safety behavior of construction workers. J Manag Eng. (2022) 38:04021074. doi: 10.1061/(ASCE)ME.1943-5479.0000977

Crossref Full Text | Google Scholar

51. Xia N, Tang Y, Li D, Pan A. Safety behavior among construction workers: influences of personality and leadership. J Constr Eng Manag. (2021) 147:04021019. doi: 10.1061/(ASCE)CO.1943-7862.0002023

Crossref Full Text | Google Scholar

52. Qiu H. Principle and Application of Structural Equation Model. Beijing, China: China Light Industry Press. (2009).

Google Scholar

53. Wu M. Structural Equation Model – Operation and Application of Amos. Chongqing, China: Chongqing University Press. (2009).

Google Scholar

54. Qin Y, Zhang J, Jia X, Hui Y, Cui C. Safety evaluation for the overtaking behavior on the two-lane highway based on the structural equation model. J Safety Environ. (2017) 17:1359–64.

Google Scholar

55. Sui K, Meng Y, Yan X, Zhou X. Pls-sem-based analysis on contruction safety of water conservancy project. Water Resour Hydrop Eng. (2019) 50:115–9.

Google Scholar

56. Duan Y, Zhou S, Guo Y, Wang X. Safety risk and strategy of prefabricated building construction based on sem. J Civil Eng Manag. (2020) 37:70–121.

Google Scholar

57. He Y, Fan Z. Research on double-weight risk assessment method of coal mine safety managemen. J Xi'an Univ Sci Technol. (2022) 42:600–6.

Google Scholar

58. Jiang J, Li X, Xing L, Chen Y. System risk analysis and evaluation approach based on fuzzy evidential reasoning. Syst Eng Theory Pract. (2013) 33:529–37.

Google Scholar

59. Gao J, Zhang H, Men G, Wang Q. A fuzzy evidence reasoning method for aviation safety risk evaluation. Electr Opt Control. (2022) 29:81–113.

Google Scholar

60. Yang J, Wang Y, Xu D, Chin K. The evidential reasoning approach for MADA under both probabilistic and fuzzy uncertainties. Eur J Oper Res. (2006) 171:309–43. doi: 10.1016/j.ejor.2004.09.017

Crossref Full Text | Google Scholar

61. Zhang Z, Wang B, Wang X, He Y, Wang H, Zhao SB. Safety-risk assessment for TBM construction of hydraulic tunnel based on fuzzy evidence reasoning. Processes. (2022) 10:2597. doi: 10.3390/pr10122597

Crossref Full Text | Google Scholar

62. Pan X, Chen G, Peng M. Risk Assessment on shield excavation in very large tunnel across Qiantang river. Chin J Undergr Space Eng. (2007) 22:1245–54.

Google Scholar

63. Liu Y, Wang J, Wu H. Dbn-based dynamic evolution analysis of safety risk in underwater metro shield construction. Railway Standard Design. (2021) 65:141–8.

Google Scholar

64. Shao X, Yao H, Zhang Z, Lu K, Hu Z. Numerical simulation analysis of Hefei metro shield tunnel crossing river. J Heifei Univ Technol. (2017) 40:95–100.

Google Scholar

65. Fang Q, Wang J, Liu X, Song R. Characteristics of ground deformation induced by large-diameter slurry shield construction. Modern Tunnell Technol. (2017) 54:120–5.

Google Scholar

66. Deng C, Gan L, Deng J, Feng X. Risk elimination and reinforcement technology of anti-seepage for river embankment in tunnel crossing section. Adv Sci Technol Water Resour. (2022) 42:80–4.

Google Scholar

67. Li C, Wang Z, Liu Q. Numerical simulation of mudstone shield tunnel excavation with Abaqus seepage-stress coupling: a case study. Sustainability. (2023) 15:667. doi: 10.3390/su15010667

Crossref Full Text | Google Scholar

68. Li X, Wang C, Kassem MA, Alhajlah H, Bimenyimana S. Evaluation method for quality risks of safety in prefabricated building construction using SEM-SDM approach. Int J Environ Res Public Health. (2022) 19:5180. doi: 10.3390/ijerph19095180

PubMed Abstract | Crossref Full Text | Google Scholar

69. Li X, Wang C, Kassem MA, Zhang Z, Xiao Y, Lin M. Safety risk assessment in urban public space using structural equation modelling. Appl Sci-Basel. (2022) 12:12318. doi: 10.3390/app122312318

Crossref Full Text | Google Scholar

70. Wang Q, Xiong Z, Zhu K, Guo P. Construction safety risks of metro tunnels constructed by the mining method in Wuhan city, china: a structural equation model-fuzzy cognitive map hybrid method. Buildings. (2023) 13:1335. doi: 10.3390/buildings13051335

Crossref Full Text | Google Scholar

71. Zhang L, Wu X, Zhu H, AbouRizk SM. Perceiving safety risk of buildings adjacent to tunneling excavation: an information fusion approach. Autom Constr. (2017) 73:88–101. doi: 10.1016/j.autcon.2016.09.003

Crossref Full Text | Google Scholar

72. Cai Q, Hu Q, Ma G. Improved hybrid reasoning approach to safety risk perception under uncertainty for mountain tunnel construction. J Constr Eng Manage. (2021) 147:04021105. doi: 10.1061/(ASCE)CO.1943-7862.0002128

Crossref Full Text | Google Scholar

73. Zhang L, Ding L, Wu X, Skibniewski M. An improved dempster-shafer approach to construction safety risk perception. Knowl Based Syst. (2017) 132:30–46. doi: 10.1016/j.knosys.2017.06.014

Crossref Full Text | Google Scholar

74. Zhang W, Zhu S, Zhang X, Zhao T. Identification of critical causes of construction accidents in china using a model based on system thinking and case analysis. Saf Sci. (2020) 121:606–18. doi: 10.1016/j.ssci.2019.04.038

Crossref Full Text | Google Scholar

75. Wu C, Yao H, Ning X, Wang L. Emergence of informal safety leadership: a social-cognitive process for accident prevention. Prod Oper Manage. (2021) 30:4288–305. doi: 10.1111/poms.13523

Crossref Full Text | Google Scholar

76. Zhang L, Chen H, Li H, Wu X, Skibniewski MJ. Perceiving interactions and dynamics of safety leadership in construction projects. Saf Sci. (2018) 106:66–78. doi: 10.1016/j.ssci.2018.03.007

Crossref Full Text | Google Scholar

77. Xia N, Xie Q, Hu X, Wang X, Meng H, A. dual perspective on risk perception and its effect on safety behavior: a moderated mediation model of safety motivation, and supervisor's and coworkers' safety climate. Accid Anal Prev. (2020) 134:105350. doi: 10.1016/j.aap.2019.105350

PubMed Abstract | Crossref Full Text | Google Scholar

78. Xia N, Xie Q, Griffin MA, Ye G, Yuan J. Antecedents of safety behavior in construction: a literature review and an integrated conceptual framework. Accid Anal Prev. (2020) 148:105834. doi: 10.1016/j.aap.2020.105834

PubMed Abstract | Crossref Full Text | Google Scholar

79. Chen H, Gong W, Li H, Shi S. Co-workers' guanxi and construction workers' safety behavior: the mediating role of group identification. Front Public Health. (2022) 10:964514. doi: 10.3389/fpubh.2022.964514

PubMed Abstract | Crossref Full Text | Google Scholar

80. Yiu NSN, Chan DWM, Shan M, Sze NN. Implementation of safety management system in managing construction projects: benefits and obstacles. Saf Sci. (2019) 117:23–32. doi: 10.1016/j.ssci.2019.03.027

Crossref Full Text | Google Scholar

81. Yue S, Fang P, Lu H, Jiang H, Zhang J. Quantitative analysis of the factors affecting the face instability of a river-crossing shield tunnel of the nanjing metro. Modern Tunnell Technol. (2013) 50:112–7.

Google Scholar

82. Wang F. Research on design difficulties and project argumentation about the yellow river tunnel of lanzhou metro. J Railway Eng Soc. (2014) 31:62–83.

Google Scholar

Keywords: shield construction safety risks assessment, subway under-crossing a river, safety risk list, safety assessment model, confirmatory factor analysis, fuzzy evidence reasoning

Citation: He K, Cui T, Cheng J, Huang Y, Li H, Chen H and Yang K (2024) Safety risk assessment of subway shield construction under-crossing a river using CFA and FER. Front. Public Health 12:1279642. doi: 10.3389/fpubh.2024.1279642

Received: 18 August 2023; Accepted: 12 January 2024;
Published: 02 February 2024.

Edited by:

Marc Bascompta, Universitat Politecnica de Catalunya, Spain

Reviewed by:

Federica Caffaro, Roma Tre University, Italy
Changquan He, Shanghai Normal University, China

Copyright © 2024 He, Cui, Cheng, Huang, Li, Chen and Yang. This is an open-access article distributed under the terms of the Creative Commons Attribution License (CC BY). The use, distribution or reproduction in other forums is permitted, provided the original author(s) and the copyright owner(s) are credited and that the original publication in this journal is cited, in accordance with accepted academic practice. No use, distribution or reproduction is permitted which does not comply with these terms.

*Correspondence: Yanlong Huang, 212108020025@home.hpu.edu.cn

Disclaimer: All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article or claim that may be made by its manufacturer is not guaranteed or endorsed by the publisher.