COMMUNITY CASE STUDY article

Front. Public Health, 28 July 2020
Sec. Public Health Policy

Transforming a General Hospital to an Infectious Disease Hospital for COVID-19 Over 2 Weeks

\nNavin PandeyNavin Pandey1Vipin KaushalVipin Kaushal1Goverdhan Dutt PuriGoverdhan Dutt Puri2Sunil TanejaSunil Taneja3Manisha BiswalManisha Biswal4Pranay MahajanPranay Mahajan1Rashmi Ranjan GuruRashmi Ranjan Guru1Pankaj MalhotraPankaj Malhotra5Inderpaul Singh SehgalInderpaul Singh Sehgal6Sahajal DhooriaSahajal Dhooria6Valliappan MuthuValliappan Muthu6Ritesh Agarwal
Ritesh Agarwal6*
  • 1Department of Hospital Administration, Postgraduate Institute of Medical Education and Research, Chandigarh, India
  • 2Department of Anesthesia and Critical Care, Postgraduate Institute of Medical Education and Research, Chandigarh, India
  • 3Department of Hepatology, Postgraduate Institute of Medical Education and Research, Chandigarh, India
  • 4Department of Medical Microbiology, Postgraduate Institute of Medical Education and Research, Chandigarh, India
  • 5Department of Internal Medicine, Postgraduate Institute of Medical Education and Research, Chandigarh, India
  • 6Department of Pulmonary Medicine, Postgraduate Institute of Medical Education and Research, Chandigarh, India

Pandemics like the coronavirus disease (COVID)-19 can cause a significant strain on the healthcare system. Healthcare organizations must be ready with their contingency plans for managing many patients with contagious infectious disease. Ideally, every large hospital should have a facility that can function as a high-level isolation unit. An isolation unit ensures that the healthcare staff and the hospital are equipped to deal with infectious disease outbreaks. Unfortunately, such facilities do not exist in several hospitals, especially in resource-limited settings. In such a scenario, healthcare setups need to convert their existing general structure into an infectious disease facility. Herein, we describe our experience in transforming a general hospital into a functional infectious disease isolation unit.

Introduction

An outbreak of pneumonia of unknown origin was reported from the Wuhan province of China in December 2019. Subsequently, the pneumonic illness was found to be caused by a novel coronavirus (CoV) resembling the severe acute respiratory syndrome (SARS) virus (1). The World Health Organization (WHO) named the virus as SARS-CoV-2 and the disease as Coronavirus Disease 19 (COVID-19) (2). Further, the disease was declared as a pandemic by the WHO on 11 March 2020 (3). Worldwide experience shows that the interventions of “social distancing,” extensive testing, and isolation of patients has helped in flattening the epidemiological curve (4). Simultaneously, the healthcare facilities (including critical care units) have to be up-scaled to handle the severely ill COVID-19 patients.

The first case of COVID-19 in India was reported in January 2020 (5). The Government of India declared a nationwide closure on 24 March 2020 as a measure to contain the spread of this pandemic (6). Meanwhile, identifying various healthcare centers in different parts of the country as isolation and treatment centers for COVID-19 became a key component to address this challenge. Our center is a tertiary-care, teaching, and referral hospital in north India. We were designated as a dedicated COVID-19 hospital for our area.

While the ideal design and facilities for a high-level isolation unit have been clearly defined (7), the problem arises when such a facility is not available. In the wake of the COVID-19 crisis, we must improvise to create the best possible facility using available resources. There is guidance available for establishing an infectious disease unit (8); however, implementation is a daunting task and requires pragmatic solutions. In general, setting up a new facility involves four main components: space, stuff (supplies), staff, and maintaining standards (9). Herein, we describe our experience in transforming a general healthcare facility to a dedicated infectious disease setup in the wake of the COVID-19 pandemic. A brief overview of the health care infrastructure in India and response to the current pandemic is outlined in Table 1 (1013).

TABLE 1
www.frontiersin.org

Table 1. Brief overview of health care infrastructure in India and response to the COVID-19 pandemic.

Administrative Setup of Our Center

Our Institute is a public sector tertiary care research hospital directly governed by the Ministry of Health and Family Welfare (India). The Director is the CEO equivalent of the Institute followed by the Dean. In the current pandemic, the Director constituted several committees, and the one for the COVID hospital was chaired by the Dean (GDP) with several members who took various decisions. The members were from the hospital administration (RRG, PM, NP, and VK), pulmonary medicine (VM, ISS, SD, and RA), infection control (MB), and internal medicine (ST and PM). The committee then brainstormed for 2 days and outlined the important initial tasks. The tasks were then completed in a time-bound fashion with the help of the hospital engineering, hospital procurement team, and countless other staff.

There were certain important policy decisions beyond this hospital. The decision for a separate COVID hospital was undertaken by the government of India such that the non-COVID essential patient care continues unimpeded. The non-essential services were, however, curtailed not only as an infection prevention measure but also to divert the resources toward effectively handling the pandemic. The essential services such as emergency, intensive care unit, bronchoscopy, and others were continued.

Problem No. 1: Identification of a Dedicated Site For the Infectious Disease Hospital

The first challenge was identifying a dedicated site for managing COVID-19 patients. Ideally, a hospital block that can be separated from the main hospital should be identified (14). Else, an area that can be physically isolated from routine services is also acceptable (15). We were fortunate to have a ready-to-use 200-bed newly constructed hospital physically separate from the main hospital. Most situations will not have such good fortune; hence, reliance on temporary hospitals will be required (1618). However, such temporary facilities can handle only mild to moderate cases and not those requiring intensive care. A few departments that had started functioning in the new building of our hospital were relocated to their original sites. The building is designed in the form of six rectangular blocks interconnected at one end through a common corridor (Figure 1). The design resembles a comb with the corridor representing the shaft and the blocks representing the comb's teeth. There are five levels and a basement. The intensive care units (ICUs), high dependency units (HDUs), and operating theaters (OTs) are housed at the fifth level (total capacity of 50 ICU/HDU beds). The fourth level consists of 50 independent rooms. The third and the second levels have general wards and a few independent rooms, with a total capacity of 100 patients. In total, the new hospital could cater to about 200 patients. The reception and administrative offices are located on the ground floor (Level 1). The basement has the facility for the central store (for equipment, drugs, linen, and others).

FIGURE 1
www.frontiersin.org

Figure 1. A model of the hospital transformed to function as COVID-19 facility. The design resembles a comb with the corridor representing the shaft and the blocks representing the comb's teeth. There are five levels and a basement.

We decided that the fourth and fifth levels will be utilized first. Subsequently, with increasing patient numbers, we planned the utilization of the third and the second levels. The ICU and pre- and post-operative rooms (collectively labeled the HDU) on the fifth level were demarcated for critically ill patients, while single rooms on the fourth level were allocated for isolating relatively stable patients. A single OT on the fifth level was selected for performing any surgeries on COVID-19 patients.

Practice Points

• Choose a separate building to function as an infectious disease facility, away from the non-COVID hospital. If such a facility is not available, identify an area that is physically disconnected from the general non-COVID area, with a separate entry and exit.

Problem No. 2: Shifting of Equipment For Use in the COVID Hospital

The newly established hospital lacked facilities for managing critically ill patients, as the purchase of equipment was delayed owing to the lockdown. The departments of anesthesia and pulmonary medicine got together and made a checklist of requisites to run an ICU. We then used the various departments' existing inventory to stockpile the new ICU with the necessary supplies and medications. Subsequently, we quickly shifted the supplies from their respective areas for use in the COVID complex. These included ICU ventilators, defibrillators, monitors, crash carts, and other consumables. Further, we mobilized the portable electrocardiography and radiology machines, dialysis machines, and a point-of-care blood analyzer for use in the ICU. We implemented standard infection control practices, including the use of a separate stethoscope, thermometer, sphygmomanometer, and others in the patient care areas. One staff from each department was present throughout the initial week to mobilize the equipment, as required.

Practice Points

• Create a checklist and mobilize the existing resources to initiate hospital services. A multidisciplinary team approach helps in the pooling of resources during a crisis.

Problem No. 3: Streamlining the Movement of Patients and Healthcare Workers

An important consideration was delineating the flow of patients and the hospital staff to ensure the demarcation of contaminated (dirty), semi-clean, and clean areas. We identified the hospital block at the farthest end of the hospital premises as the point of entry for patients (Figure 2, block C2). We identified a single elevator in that block for the movement of patients to different floors. A triage area was set up in this block near the entrance. The patient was transported from the triage area to the respective floors through a dedicated (“contaminated”) elevator (Figure 2). This entire zone was labeled a contaminated zone, and barriers were installed to guarantee no movement of staff or materials from this zone to the rest of the block on this level (Figure 2, block C2). We delineated a separate entry for the movement of the staff posted on different levels, thereby completely avoiding an intersection between the two paths. We dedicated a floor-to-floor inclined ramp for the transfer of patient samples in closed boxes; this area was designated as relatively clean. The staff movement zone was also considered a relatively clean zone. Finally, a clean zone was created on the ground floor (Level 1) with a single entry and exit through the main reception area, different from the two abovementioned zones. The clean area was meant for use by the staff not directly involved in patient care (administrative staff, material transfer, and others). An elevator identified in the clean area on level 1 was used for the transfer of clean materials to different levels without physically “getting down” on the respective floor.

FIGURE 2
www.frontiersin.org

Figure 2. A schematic representation of the functioning of the transformed hospital. A clear demarcation between the clean and contaminated zone can be appreciated in the picture.

Practice Points

• Plan the infectious disease facility, taking care that the most infectious patients are kept away from the common entry points.

• We must ensure a clear boundary between contaminated, relatively clean, and clean zones.

Problem No. 4: Identifying Areas For Donning and Doffing of Personal Protective Equipment (PPE)

We converted one office room into a space for storage, distribution, and audit of PPE. A store assistant was posted in this area to distribute PPE and assure rational utilization. We arranged a snack counter in this area for the staff who are to perform the ICU shifts, as the PPE had to be worn for the next 6 h. A common donning area consisting of individual rooms was created near the staff entrance area (Figure 2, block C1) by converting four office spaces into changing rooms for the male and the female staff. We installed full-length mirrors, placed chairs, and provided for hand hygiene in the donning rooms. We placed lockers in the area adjoining the donning room for the staff to secure their belongings, including personal mobile phones. We had a contingency plan wherein an entire corridor could be converted into a donning area once the number of patients increases, and more HCWs are required in the respective areas. An elevator (semi-clean) in this block was assigned for the staff to enter the fourth and fifth levels. The elevator was programmed to stop only on the fourth and fifth levels. The security personnel ensured a one-way movement of staff, i.e., from semi-clean to contaminated zone and not vice versa.

The doffing areas are the actual problematic zones, and meticulous planning is required while designing these areas. We identified two rooms, each on the fourth and the fifth levels, as doffing areas. These rooms were located near the fire exit staircases, farthest from the common corridor (other ends of each block), thereby ideally suited for doffing (Figure 2). The doffing rooms had two separate doors, one for entry and the other for exit. We partitioned the doffing area into clean and dirty zones, installed full-length mirrors, and placed hand sanitizers. We also installed exhaust fans to improve air circulation. Immediately after doffing, the staff had to exit through the fire exit staircases and make their way back through the same staff entry gate (Figure 2, block C1). We earmarked a few rooms for de-scrubbing on level 1, where the HCWs had to remove their scrubs and shower before changing into their usual clothes. The de-scrub rooms also had full-length mirrors, appropriate waste disposal bins, hand sanitizers, and masks. We also made provisions for light snacks at the exit point.

Practice Points

• Identify and label all entry, exit, stairs, and escalators to prevent the intersection of clean and contaminated paths.

• Provide facilities for refreshment, shower, and lockers in the donning and de-scrub areas. This area should be separate from the contaminated zone.

Problem No. 5: Air Conditioning and Air Distribution

The hospital was originally not meant for highly contagious infectious disease patients. The heating, ventilation, and air conditioning (HVAC) system of the building was designed for recirculation of air inside the premises. Moreover, the HVAC system had a capacity only for six air exchanges per hour and no provision for a negative pressure unit. We made the following modifications. We sealed the return ducts in the ICU and HDU areas to prevent the recirculation of air. Further, we installed exhaust fans in the ICU, HDU, and doffing areas to ensure at least 12 air exchanges per hour (19, 20). In places where the return ducts could not be sealed (like the corridors), the air-conditioning was switched off, and the smoke exhaust system was used every 2 h to push the air out and allow fresh air. Exhausts were present in the toilets of individual patient rooms. Additionally, the windows were kept open in patients' rooms and corridors to enhance natural ventilation.

Practice Points

• Prevent recirculation of air and assure at least 12 exchanges per hour. Utilize low-cost systems such as simple exhaust fans for air exchanges.

Problem No. 6: Lack of Trained Manpower to Work in an Infectious Disease Facility

We decided that the HCWs would work for 7 days. During the 7-day duty period, the staff was provided accommodation within the hospital campus. Quarantine facilities were created for these staff by vacating individual private rooms in a separate building of the hospital. The HCWs in this setup were expected to be in a PPE for the entire duration of their shift; hence, we restricted the duty to 6 h. However, these measures of limited duty periods and prolonged quarantine required many HCWs. Our Institute routinely caters to around 10,000 patients in the outpatient department every day. Given the ongoing nationwide lockdown, we curtailed the outpatient services, elective admissions, and surgeries as a measure to reduce overcrowding. The staff employed in all these services were allocated to the new facility. The new staff posed a challenge as the HCWs were inexperienced with the different protocols of a respiratory isolation unit. To overcome this problem, we trained the HCWs on an urgent basis. Several teams were created to impart training with the ICU protocols, infection control practices, including the donning and doffing of PPE, and the movement of staff, patients, and materials inside this new facility. The auxiliary staff delivering services like hospital engineers, security guards, dieticians, epidemiologists, and ambulance drivers were also trained in appropriate PPE and other relevant infection control protocols. We installed closed-circuit television (CCTV) cameras and public address systems in the doffing areas for real-time monitoring. A control room was activated to continuously monitor CCTV outputs of the clinical areas to identify any discrepancies and apprehend any breaches in the established protocols.

Practice Points

• Curtail non-essential hospital services to reallocate the HCWs for dealing with the pandemic.

• Provide intensive training in the ICU and infectious disease practices for the newly recruited HCWs.

• Employ telemonitoring of the HCWs to ensure adherence to the laid down protocols.

Problem No. 7: Arranging the Requisite Personal Protective Equipment

Since the onset of this pandemic, photographs, and videos of HCWs in hazmat suits had become commonplace. Most HCWs were convinced that this was mandatory for patient care. Initially, we did not have enough supplies to meet the anticipated demand for PPE. We decided on a PPE kit consisting of the following items namely, hospital scrubs, surgical cap, water-impervious surgical gown with a hood, an overall surgical gown (sterile gowns for the OTs, ICU, and HDU), protective goggles, N95 mask, visor, knee-length shoe cover, surgical mask, and two pairs of gloves. The procurement of PPE was a daunting task as the supply chain was interrupted owing to the nationwide lockdown. To maintain the supply chain, we decided to stockpile all the necessary PPE required for at least a month's duration. Fortunately, the textile companies responded to the government's plea and started the manufacture of various components of PPE. In fact, India is currently the second largest manufacturer of PPE worldwide and is considering export (21). We contacted local manufacturers and vendors. The samples from different vendors were evaluated by an expert committee comprising of a microbiologist, internist, pulmonologist, and hospital management. No single supplier could provide the products mentioned above of good quality in a single package. Hence, we purchased the individual components of the PPE from different manufacturers. A team of hospital staff then assembled the individual items in a single package. By the time we had 15 patients in this new setup, we were utilizing around 70 PPEs in a day consisting of four duty shifts.

Practice Points

• In the absence of a supply of standard PPE, utilize local vendors to supply the individual items, which can then be assembled in a single package. However, one must ascertain that strict quality control measures are in place.

• Involve end-users in evaluating the appropriateness of PPE.

Problem No. 8: Provision of Laboratory and Radiology Services

A portable machine for radiography and ultrasound machines were placed in the patient care areas. Technicians were trained in the donning and doffing process and were available on call. We mobilized a point-of-care arterial blood gas analyzer from another area for use in the ICU. We provided separate iceboxes in all clinical areas for the storage of virology swabs and other samples. The vacutainer tubes were stored in Ziplock bags in these icebox containers. We instructed all the staff in the clinical areas to have the icebox containers placed at the entrance of the inclined ramp identified for the transport of samples on the respective floors. A hospital attendant would reach the respective levels through the designated ramp (relatively clean zone). The attendant would then transfer the contents of the ward icebox to a clean icebox. The clean icebox would subsequently be transported to the sample collection area. The samples were transported to the respective laboratories by laboratory personnel at a fixed time every day. We used WhatsApp to implement a paperless request for investigations and receiving reports, to strengthen our infection control practice further.

Practice Points

• It may not be possible to have the complete support of routine services like laboratory, radiology, and others within a new infectious disease setup. Therefore, develop simple protocols for handling the samples and conducting radiological investigations to minimize cross-contamination.

Problem No. 9: Development of Standard Operating Procedures (SOPs)

Hospitals are typical matrix organizations with various departments and a blurred line of staff control (22). Hence, SOPs are integral for the functioning of any hospital (23). We developed SOPs for all the support services, as described below.

Dietetics, Pharmacy, and Other Supplies

To minimize the exposure of hospital staff involved in the delivery of various materials, we undertook the following steps. A nursing officer in the clean zone was made responsible for coordinating and procuring all the materials required for patient care. We provided smart phones at the nursing stations of the patient care areas (contaminated) at each floor for easy communication with the coordinating nurse (clean) and other staff.

We used disposable cartons for the transfer of all materials to decrease the risk of infection. The boxes were transported to the respective floors through an elevator in the clean zone (Figure 2, level 1, block B2) by a hospital attendant. This elevator could only be operated from outside on the first level, thereby ensuring that no HCW from the contaminated zone could use the elevator to reach the ground floor (first level). The attendant would push the package outside the lift on the respective floor without stepping out. The cartons were then picked up by another hospital attendant on the floor and discarded after use from the patient care areas like other biomedical waste (BMW).

Laundry

All linen from patient care areas were immersed in 1% sodium hypochlorite solution for a period of half an hour (24). The disinfected linen was then transported by a laundry attendant wearing PPE using an elevator adjoining the one used for patient movement in the contaminated area (the “contaminated elevator for BMW”).

Biomedical Waste

We anticipated a substantial amount of BMW to be generated in every shift because of the extensive use of PPE by all staff involved in service delivery. We decided that all the generated waste would be collected in double bags and disinfected as per the current guidelines (25). Personnel donned in PPE from the BMW department would visit these areas in every shift with their transport trolley using the “contaminated elevator for BMW.”

Discharge

The same route by which the patients enter was also used for discharge. COVID-19 had created a unique situation wherein, at times, no patient attendants are available at the time of discharge of patients. The social stigma associated with the disease compounded the problem further. Thus, we needed to drop these patients to their homes by ambulance.

Death

After the demise of the patient, the body was wrapped in double body bags, and shifted to the mortuary by trained personnel donned in PPE. The local governing body undertook the responsibility of transportation from the hospital mortuary to the area dedicated to performing the last rites (26). The ambulance used to carry patients to the hospital or the dead bodies to mortuary was disinfected using 1% sodium hypochlorite between patients.

Practice Points

• Develop standard operating protocols for support staff to provide efficient and unhampered service.

Problem No. 10: Psychological Support for the HCWs

We anticipated tremendous stress would occur on the HCWs involved in COVID-19 care for various reasons. These include the highly infectious nature of the illness, working in a new environment wearing the PPE, potential risk of infecting themselves and their loved ones, inability to cope with the uncertainties surrounding the pandemic, being distanced from their family during a week-long duty, and news reports of death amongst the HCWs. A dedicated team from the department of psychiatry provided psychosocial support to HCWs and their families on a round-the-clock basis. We established a 24-h helpline number to assist them in this task.

Practice Points

• Tremendous stress is expected amongst the HCWs and their families during such pandemics. Extend psychosocial support that is readily available and accessible.

Conclusions

Disasters, especially a pandemic like COVID-19, demand a sudden change in all pre-existing practices. The most crucial point that we have learned from this pandemic is the need for disaster preparedness. Every hospital needs to maintain a contingency of resources and have an active infection control and disease outbreak team in place. Before any hospital management, the challenge is to come up with solutions that are scientific, practical, and simple enough to be implemented and adopted by the multiple categories of staff in a hospital. We have provided a broad outline for transforming a general hospital into an infectious disease hospital. Importantly, the changes that we made to the hospital are temporary, ensuring that we can bounce back to normal quickly once the pandemic subsides. However, the lessons learned have long-lasting implications for policymakers.

Data Availability Statement

The original contributions presented in the study are included in the article/supplementary material, further inquiries can be directed to the corresponding author/s.

Author Contributions

NP, VK, GP, ST, MB, PMah, RG, PMal, IS, SD, VM, and RA drafted and revised the manuscript. All authors contributed to the article and approved the submitted version.

Conflict of Interest

The authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Acknowledgments

The transformation of this hospital was a massive teamwork of the entire hospital including administrators and countless hospital staff.

References

1. Zhu N, Zhang D, Wang W, Li X, Yang B, Song J, et al. A novel coronavirus from patients with pneumonia in China, 2019. N Engl J Med. (2020) 382:727–33. doi: 10.1056/NEJMoa2001017

PubMed Abstract | CrossRef Full Text | Google Scholar

2. WHO. WHO Disease Outbreak News. Pneumonia of unknown cause – China (2020). Available online at: https://www.who.int/csr/don/05-january-2020-pneumonia-of-unkown-cause-china/en/ (accessed April 16, 2020).

3. WHO. WHO Director-General's Opening Remarks at the Media Briefing on COVID-19 - 11 March 2020. (2020). Available online at: https://www.who.int/dg/speeches/detail/who-director-general-s-opening-remarks-at-the-media-briefing-on-covid-19–11-march-2020 (accessed April 16, 2020).

4. Pan A, Liu L, Wang C, Guo H, Hao X, Wang Q, et al. Association of public health interventions with the epidemiology of the COVID-19 outbreak in Wuhan, China. JAMA. (2020) 323:1915–23. doi: 10.1001/jama.2020.6130

PubMed Abstract | CrossRef Full Text | Google Scholar

5. Unnithan PSG. Kerala Reports First Confirmed Coronavirus Case in India. India Today (2020). Available online at: https://www.indiatoday.in/india/story/kerala-reports-first-confirmed-novel-coronavirus-case-in-india-1641593-2020-01-30 (accessed April 16, 2020).

6. Wikipedia. 2020 Coronavirus Lockdown in India. (2020). Available online at: https://en.wikipedia.org/wiki/2020_coronavirus_lockdown_in_India (accessed April 16, 2020).

7. Bannister B, Puro V, Fusco FM, Heptonstall J, Ippolito G. Framework for the design and operation of high-level isolation units: consensus of the European network of infectious diseases. Lancet Infect Dis. (2009) 9:45–56. doi: 10.1016/S1473-3099(08)70304-9

PubMed Abstract | CrossRef Full Text | Google Scholar

8. Agarwal A, Nagi N, Chatterjee P, Sarkar S, Mourya D, Sahay RR, et al. Guidance for building a dedicated health facility to contain the spread of the 2019 novel coronavirus outbreak. Indian J Med Res. (2020) 151:177–83. doi: 10.4103/ijmr.IJMR_518_20

PubMed Abstract | CrossRef Full Text | Google Scholar

9. Goh KJ, Wong J, Tien JC, Ng SY, Duu Wen S, Phua GC, et al. Preparing your intensive care unit for the COVID-19 pandemic: practical considerations and strategies. Crit Care. (2020) 24:215. doi: 10.1186/s13054-020-02916-4

PubMed Abstract | CrossRef Full Text | Google Scholar

10. CBHI. National Health Profile 2019. 14th Issue. Central Bureau of Health Intelligence. Directorate General of Health Services. Government of India (2019). Available online at: http://www.cbhidghs.nic.in/showfile.php?lid=1147 (accessed June 17, 2020).

11. Gupta A, Singla R, Caminero JA, Singla N, Mrigpuri P, Mohan A. Impact of COVID-19 on tuberculosis services in India. Int J Tuberc Lung Dis. (2020) 24:637–9. doi: 10.5588/ijtld.20.0212

PubMed Abstract | CrossRef Full Text | Google Scholar

12. MOHFW. Guidance Document on Appropriate Managem ent of Suspect/Confirmed Cases of COVID-19. (2020). Available online at: https://www.mohfw.gov.in/pdf/FinalGuidanceonMangaementofCovidcasesversion2.pdf (accessed June 17, 2020).

13. MOHFW. SOP for Reallocation of Residents/PG Students and Nursing Students as Part of Hospital Management of COVID. (2020). Available online at: https://www.mohfw.gov.in/pdf/COVID19SOPfordoctorsandnurses.pdf (accessed June 17, 2020).

14. Bataille J, Brouqui P. Building an intelligent hospital to fight contagion. Clin Infect Dis. (2017) 65:S4–11. doi: 10.1093/cid/cix402

PubMed Abstract | CrossRef Full Text | Google Scholar

15. Asperges E, Novati S, Muzzi A, Biscarini S, Sciarra M, Lupi M, et al. Rapid response to COVID-19 outbreak in Northern Italy: how to convert a classic infectious disease ward into a COVID-19 response centre. J Hosp Infect. (2020) 105:477–9. doi: 10.1016/j.jhin.2020.03.020

PubMed Abstract | CrossRef Full Text | Google Scholar

16. AHA. Leading during COVID-19: Lessons Learned from Clinical and Administrative Teams. (2020). Available online at: https://www.aha.org/podcasts/2020-05-28-leading-during-covid-19-lessons-learned-clinical-and-administrative-teams (accessed June 18, 2020).

17. Cheney C. Coronavirus: 5 Lessons Learned from Temporary Hospitals in China. (2020). Available online at: https://www.healthleadersmedia.com/clinical-care/coronavirus-5-lessons-learned-temporary-hospitals-china (accessed June 18, 2020).

18. Listed NA. Michigan National Guard Building Temporary Medical Station in Detroit to Support Coronavirus Patients. (2020). Available online at: https://www.mlive.com/public-interest/2020/04/michigan-national-guard-building-temporary-medical-station-in-detroit-to-support-coronavirus-patients.html (accessed June 18, 2020).

19. CDC. CDC Guidelines for Environmental Infection Control in Health-Care Facilities. (2003). Available online at: https://www.cdc.gov/infectioncontrol/guidelines/environmental/appendix/air.html (accessed April 16, 2020).

Google Scholar

20. Li Y, Huang X, Yu IT, Wong TW, Qian H. Role of air distribution in SARS transmission during the largest nosocomial outbreak in Hong Kong. Indoor Air. (2005) 15:83–95. doi: 10.1111/j.1600-0668.2004.00317.x

PubMed Abstract | CrossRef Full Text | Google Scholar

21. Ramesh M. How the 10,000-Crore PPE Industry Popped Up in Two Months. (2020). Available online at: https://www.thehindubusinessline.com/economy/how-the-10000-crore-ppe-industry-popped-up-in-two-months/article31692099.ece (accessed June 18, 2020).

22. Allcorn S. Using matrix organization to manage health care delivery organizations. Hosp Health Serv Adm. (1990) 35:575–90.

PubMed Abstract | Google Scholar

23. Rao TS, Radhakrishnan R, Andrade C. Standard operating procedures for clinical practice. Indian J Psychiatry. (2011) 53:1–3. doi: 10.4103/0019-5545.75542

PubMed Abstract | CrossRef Full Text | Google Scholar

24. UWO. Guidelines for Using Sodium Hypochlorite as a Disinfectant for Biological Waste. (2015). Available online at: https://www.uwo.ca/animal-research/doc/bleach-sop.pdf (accessed April 17, 2020).

PubMed Abstract

25. CPCB. Central Pollution Control Board Guidelines (March 18, 2020) for Handling, Treatment, and Disposal of Waste Generated during Treatment/Diagnosis/Quarantine of COVID-19 Patients. (2020). Available online at: https://www.cpcb.nic.in/uploads/Projects/Bio-Medical-Waste/BMW-GUIDELINES-COVID.pdf (accessed April 17, 2020).

26. MOHFW. Government of India. Ministry of Health and Family Welfare. Directorate General of Health Services (EMR Division). COVID-19: Guidelines on Dead Body Management. (2020). Available online at: https://www.mohfw.gov.in/pdf/1584423700568_COVID19GuidelinesonDeadbodymanagement.pdf (accessed April 17, 2020).

Keywords: hospital management, infection control, isolation unit, infectious disease hospital, COVID-19

Citation: Pandey N, Kaushal V, Puri GD, Taneja S, Biswal M, Mahajan P, Guru RR, Malhotra P, Sehgal IS, Dhooria S, Muthu V and Agarwal R (2020) Transforming a General Hospital to an Infectious Disease Hospital for COVID-19 Over 2 Weeks. Front. Public Health 8:382. doi: 10.3389/fpubh.2020.00382

Received: 04 May 2020; Accepted: 01 July 2020;
Published: 28 July 2020.

Edited by:

Connie J. Evashwick, George Washington University, United States

Reviewed by:

Stephen Michael Sammut, University of Pennsylvania, United States
James A. Rice, Gallagher HRCC, United States

Copyright © 2020 Pandey, Kaushal, Puri, Taneja, Biswal, Mahajan, Guru, Malhotra, Sehgal, Dhooria, Muthu and Agarwal. This is an open-access article distributed under the terms of the Creative Commons Attribution License (CC BY). The use, distribution or reproduction in other forums is permitted, provided the original author(s) and the copyright owner(s) are credited and that the original publication in this journal is cited, in accordance with accepted academic practice. No use, distribution or reproduction is permitted which does not comply with these terms.

*Correspondence: Ritesh Agarwal, agarwal.ritesh@outlook.in

Disclaimer: All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article or claim that may be made by its manufacturer is not guaranteed or endorsed by the publisher.