Skip to main content

ORIGINAL RESEARCH article

Front. Energy Res., 05 January 2023
Sec. Process and Energy Systems Engineering
This article is part of the Research Topic Advanced Technologies for Planning and Operation of Prosumer Energy Systems, volume II View all 30 articles

A novel investment strategy for renewable-dominated power distribution networks

Zhao Fei
Zhao Fei1*Xue LongjiangXue Longjiang2Zhu JingliangZhu Jingliang1Chen DingChen Ding1Fang JinghuiFang Jinghui2Wu JunWu Jun2
  • 1State Grid Jiaxing Electric Power Supply Company, Jiaxing, Zhejiang, China
  • 2State Grid Zhejiang Electric Power Co., Ltd., Pinghu Power Supply Company, Zhejiang, Pinghu, China

Aiming at the problem of insufficient adaptability to the new elements of the new power system in the current distribution network investment method, this paper innovatively proposes a distribution network investment method based on the new power system. By constructing a source-grid-load-storage-side investment calculation model, the investment in the new power system can be accurately calculated. First, the distributed power investment is calculated from the two aspects of new construction and renovation. Secondly, construct the grid investment demand and grid investment capacity measurement model, and obtain the grid side investment model by weighted summation. Then, a model for calculating the scale of investment that can be saved due to demand-side response is constructed, and the cost of demand response is subtracted to obtain a model for calculating the scale of investment that can be saved on the load side. Finally, the energy storage side investment calculation model is constructed from the power supply side, grid side, user-side energy storage investment, and energy storage investment benefit. The research results are applied to the empirical area, and scientific guidance is provided to realize the precise investment in the area.

1 Introduction

Building a new type of power system is an all-round change, a very challenging and pioneering strategic project (Sánchez et al., 2022). From the perspective of power grid investment, the investment structure and focus will undergo major changes (He et al., 2022). Power grid enterprises should actively implement the reform of management methods (Zhu et al., 2022), change investment concepts and thinking in a timely manner, accurately grasp the focus and direction of investment, optimize investment strategies (Zhang et al., 2022), and provide sufficient and accurate investment support for the construction of new power systems.

At present, experts and scholars have conducted much research on distribution network investment methods. Reference (Ren et al., 2019)estimates the size of the distribution network based on the current situation and load growth of the distribution network, and proposes a model strategy for distribution network investment allocation in combination with regional development needs, economic and social benefits of investment. Reference (Zheng et al., 2021) establishes an improved comprehensive evaluation method and evaluation model of distribution network investment benefit based on the individual evaluation results of investment benefit of distribution network reconstruction project, combined with information entropy and fuzzy analysis method. Reference (Wu et al., 2019)starts from technology, benefit, and project maturity, and builds an index system for investment ranking and evaluation of power grid planning projects under the new power reform environment. The precise investment decision of the distribution network in the above literature is mainly aimed at the traditional power system and has insufficient adaptability to the new elements of the new power system.

In order to implement the dual carbon goal, the state proposes to build a new power system with new energy as the main body. Compared with the traditional power system, its core feature is that new energy occupies a dominant position. In the future, wind power, photovoltaics, and energy storage will show explosive growth. Reference (Elkadeem et al., 2019) proposes an optimal investment model for a distribution network with renewable energy that considers efficiency, benefit, and carbon emission reduction. Based on the research of regional multi-energy system model, reference (Nazir et al., 2021) proposes a regional renewable energy generation capacity planning and investment benefit optimization model based on different dispatch time scales. Reference (Gao and Zhao, 2018) used system dynamics and evolutionary game methods to study the willingness of all parties to photovoltaic projects under the contract energy management model. Although the above references all add new elements related to renewable energy and storage, they do not fully consider the impact of new elements on the investment and construction of the new power system on the four sides of the source, network, load and storage.

In order to adapt to the new elements of the new power system, this paper proposes a distribution network investment method based on the new power system. By constructing the four-side investment model of source, network, load, and storage, and predicting and analyzing the investment data of each side, the asset investment strategy of power grid enterprises can be adjusted., It is of great significance to realize precise investment and improve market competitiveness.

2 Research ideas for new power system investment methods

The general idea of research on new power system investment methods is shown in Figure 1.

FIGURE 1
www.frontiersin.org

FIGURE 1. Research idea of new power system investment method.

The formula for calculating the total investment scale of the source, grid, load, and storage side of the new power system is shown in Eq. 1:

T=C+GL+(WI)(1)

In the formula, Cis the power supply-side investment. G is the grid side investment. Lis the investment on the energy storage side. Wis the energy storage side investment. Iis the energy storage side investment, respectively.

Investment on the power supply side: In response to the need of accelerating the construction of a clean, low-carbon, safe and efficient modern energy system, taking clean development as the direction, and investing in optimizing the power supply structure on the basis of ensuring energy security.

Grid-side investment: In order to accelerate the transformation of the distribution network from a single power supply to an intelligent and interactive energy Internet, realize a first-class modern distribution network with high reliability, good interaction, economic efficiency, and reasonably and effectively meet the demand for load growth and safe and reliable power saving on the load side: the investment in the construction of high, medium, and low voltage distribution networks that can be saved due to interruptible load response, etc. Minus the cost of demand response.

Energy storage side investment: the initial cost investment of energy storage on the power supply side, the grid side, and the user side, and the operation cost investment minus the energy storage subsidy.

Energy storage side income: The income from increasing on-grid electricity, reducing the deviation of power generation plant, and providing auxiliary services is the energy storage income on the power supply side; the income such as delaying the investment in grid construction is the energy storage income on the grid side; the income such as peak-valley arbitrage is the energy storage income on the user side.

3 Research on calculation model of new power system power supply side investment

Figure 2 shows the calculation process of the investment scale of the power supply side in the future.

FIGURE 2
www.frontiersin.org

FIGURE 2. Flow chart of investment scale calculation of power supply side in future years.

The total investment scale of the power supply side is the sum of the investment in the centralized power supply and the investment in the distributed power supply. This paper mainly studies the calculation method of the investment scale of the distributed power supply (Abdelkader et al., 2018). The calculation formula is shown in Eqs. 23:

C=Cfb+Cjz(2)
Cfb=C1+C2+C3+C4(3)

In the formula, Cfbis the total investment in distributed power. Cjzthe investment in centralized power. C1and C2are the investment in the construction and reconstruction of 10 kV lines to meet the needs of distributed power supply access. C3and C4are t the construction and reconstruction of distribution transformers, respectively.

3.1 10 kV line-side distributed power investment

Considering that the tie line satisfies the N-1 check and the maximum load rate of the single radiation line does not exceed 70%, the maximum access capacity of the single-circuit 10 kV line distributed power supply is 6 MW.

1) Investment in new 10 kV lines and power distribution facilities

The calculation formula is shown in Eq. 4:

C1=a(SLDGZλSLDGZ)6(rdzPdzx+y1Pzpd+y2rdfzPdfz)+b(SLDGZλSLDGZ)6(rjzPjzx+y3Pzzs+y4rjfzPjfz)(4)

In the formula, SLDGZis the total installed capacity of the distributed power supply on the 10 kV line side; aand bare the proportions of cables and overhead lines in newly built lines respectively; λ is the current 10 kV line consumption proportion of distributed power. rdzandPdzx are the length and cost of the newly-built single-circuit 10 kV cable trunk line respectively; y1and Pzpdare the number and cost of the newly-built power distribution facilities (ring network room, branch-box) of the single-circuit cable line respectively; y2is a single distribution Number of newly-built cable branch lines for electrical facilities; rdfzand Pdfzare the unit length and cost of 10 kV cable branch lines; rjzand Pjzxare the length and cost of newly-built single-circuit 10 kV overhead main lines respectively; y3andPzzs are newly-built pole switches for single-circuit overhead lines quantity and cost; y4,rjfz, Pjfzare the number, length, and cost of newly-built branch lines of a single-circuit 10 kV overhead line, respectively.

2) Investment in transforming 10 kV lines

The calculation formula is shown in Eq. 5:

C2=(rzjk+rzjlj+rzld)Pjzx+(rzdk+rzdlj)Pdzx(5)

In the formula, rzjk,rzjlj,rzldare the current 10 kV overhead clamp neck, old and bare conductor line length respectively; rzdkand rzdljare the current 10 kV cable clamp neck and old-line length,respectively.

3.2 Distribution and transformation side distributed power investment

After calculation, the maximum distributed power access capacity SPDG of a single distribution transformer is 0.8 times the capacity of the distribution transformer.

1) Investment in new distribution transformers

The calculation formula is shown in Eq. 6:

C3=pg(SPDGZρSPDGZ)0.5×0.6Sxb(Pxb+z1rddPddx)+qg(SPDGZρSPDGZ)0.5×0.6Sp(PP+z2rdjPdjx)(6)

In the formula, SPDGZis the total installed capacity of 10 kV distribution transformer side distributed power; pis the proportion of power distribution room/box substation in newly built low-voltage equipment; gis the proportion of the current number of public transformers to the total number of distribution transformers;ρ is the proportion of distributed power supply consumed by the current distribution transformer; Sxbis the capacity of a single power distribution room/box substation. Pxbis the cost of a single power distribution room/box substation; z1,rdd andPddx are the single power distribution room/box substation, respectively the number, length, and cost of newly built low-voltage cable lines; qis the proportion of pole-mounted transformers in newly built low-voltage equipment.SPand PPare the capacity and investment of a single distribution transformer respectively; z2,rdjandPdjx are the newly built low-voltage overhead lines of a single distribution transformer number, length, and cost.

2) Investment in the transformation of distribution transformers

The calculation formula is shown in Eq. 7:

C4=tljPp+rdjljPdjx+rddljPddx(7)

In the formula, tljis the number of old distribution transformers; rdjljand rddljare the lengths of the old lines of low-voltage overhead and cables, respectively.

4 Research on calculation model of grid side investment in new power system

Figure 3 shows the calculation process of the investment scale on the grid side in the future.

FIGURE 3
www.frontiersin.org

FIGURE 3. Calculation flow chart of investment scale of grid side in future years.

The calculation formula for the investment scale on the grid side is shown in Eq. 8:

G=μg(αGxq+βGnl)(8)

In the formula,Gxqis the power grid investment demand. μgis the correction factor. Gnlis the power grid investment capacity. αandβare the investment demand of the power grid and the proportion of investment capacity, respectively, which can be determined by the analytic hierarchy process.

4.1 Grid investment demand estimation

The idea of investment demand estimation is shown in Figure 4.

1) Influencing factor system of power grid investment demand

FIGURE 4
www.frontiersin.org

FIGURE 4. Investment demand forecasting ideas.

The indicator system is shown in Figure 5.

FIGURE 5
www.frontiersin.org

FIGURE 5. Investment scale forecast influencing factors.

4.2 Correlation analysis

The selection of key impact indicators is carried out through correlation analysis (Gao et al., 2022). Correlation analysis refers to the analysis of two or more related variable elements to measure the closeness of the correlation between the two variable factors.

The calculation of the correlation coefficient is shown in Eq. 9:

r=(xx¯)(yy¯)n(xx¯)2n(yy¯)2n=(xx¯)(yy¯)(xx¯)2(yy¯)2(9)

In the formula, ris the correlation coefficient,nis the number of data items; x¯is the arithmetic mean of the independent variable seriesx;y¯is the arithmetic mean of the dependent variable seriesy.

From the correlation analysis, the key impact indicators are GDP, the number of power supply households, electricity sales, total profit, and the highest load of the whole society.

3) Forecast of the development trend of influencing factors based on gray forecast

The amount of data required for gray prediction is small. When processing the data, it does not seek the probability distribution and statistical law of the data but uses the “gray generation method” to seek a new sequence with weakened randomness and strengthened regularity. The GM (1, 1)model is used for the prediction of the development trend of the influencing factors.

The initial year index value is recorded as X(0), and the initial number column isX(0)=(X(0)(1),X(0)(2),,X(0)(n)). Reference (Luo et al., 2021) builds a model by the cumulative generation of the grey generation method, then the model is:

X^(1)(k+1)=[X(0)(1)ua]eak+ua,k=0,1,,n1(10)

By reducing the above formula, the gray prediction model of the original sequence can be obtained as:

X^(0)(k)=X^(1)(k)X^(1)(k1),k=2,3,,n(11)

4) Decision coefficient analysis based on AHP (Wang et al., 2021)

The analytic hierarchy process is used to analyze and predict the decision coefficient of key impact indicators. The calculation steps are as follows:

4.3 Establish a judgment matrix

Generally, the judgment matrix is established by the reciprocal 1–9 scale scaling method. Assuming that the judgment matrix is: A=[a11...a1m.........am1...amm], then the element aijof the judgment matrix A corresponds to the relative importance of the two elements aiand ajin the hierarchy.

4.4 Calculation method of decision coefficient

Assuming that the judgment moment is A=[a11...a1m.........am1...amm], firstly multiply each element by row and raise it to the powerm, that is, to obtain the geometric mean of the elements in each row, as shown in Eq. 12:

bi=(j=1maij)1/m(i=1,2,,m)(12)

By normalizing bi(i=1,2,,m)again, the decision coefficient of each element of the criterion layer or the scheme layer can be obtained, as shown in Eq. 13:

ωj=bjk=1mbk(j=1,2,,m)(13)

4.5 Consistency check of judgment matrix

The rationality of the decision coefficient can be verified by the consistency of the judgment matrix. If the judgment matrix can pass the consistency check, it means that the decision coefficient is reasonable; otherwise, the decision coefficient is unreasonable.

Calculate the maximum eigenvalue λmaxof the judgment matrix, as shown in Eq. 14:

λmax=1mi=1mj=1maijωjωj(14)

To calculate the consistency index C.I., the formula is shown in Eq. 15:

C.I.=λmaxmm1(15)

Define the mean consistency metric R.I..

4) Calculate the random consistency ratio C.R., the formula is shown in Eq. 16:

C.R.=C.I.R.I.(16)

The average random consistency index R.I. can be found from the Table 1 according to the matrix order m.

TABLE 1
www.frontiersin.org

TABLE 1. Average stochastic consistency indicator parameters.

4.6 Check the consistency of the judgment matrix, as follows

When C.R.=C.I.R.I.<0.1, it is considered that the judgment matrix has acceptable inconsistency, otherwise, it is considered that the initially established judgment matrix is unsatisfactory and needs to be re-assigned and carefully revised until the consistency check is passed.

5) Grid investment demand estimation

Construct an investment demand estimation model as shown in Eq. 17:

Gxq=i=1nui×[yi(k+1)yi(k)yi(k)yi(k1)]×x(k)(17)

In the formula, Gxqis the investment demand of the regional distribution network in the next year; uis the factor’s decision-making coefficient; yi(k+1)is the value of the next year’s factor; yi(k)is the value of the current year’s factor; yi(k1)is the value of the previous year’s factor; x(k)is the amount of grid input for this year.

4.7 Grid investment capacity calculation model

Figure 6 shows the calculation idea of investment capacity.

FIGURE 6
www.frontiersin.org

FIGURE 6. Investment capability forecast flow chart.

The power grid investment capacity prediction model (Yi et al., 2021) can be divided into profit subsystem, depreciation subsystem, and financing subsystem.

The investment ability prediction formula is shown in Eq. 18:

Gnl=NpTp+D+F(18)

In the formula, Gnlis the investment capacity of the power grid company. Npis the net profit of the power grid company. Tpis the profit turned over by the power grid company. Dis the depreciation amount. Fis the financing amount.

1) The net profit subsystem is shown in Eq. 19:

Np=SD+TZp+Yp+QpCBZSp(19)

In the formula, SDis the income from electricity sales. TZPis the investment income. YPis the income from the outside business. QPis the income from other businesses. CBZis the total cost and expense. SPis the income tax.

2) The depreciation subsystem is shown in Eq. 20:

D=(DZCLDZCT+ΔDZC)/N(20)

In the formula, Nis the depreciation period. DZCLis the original value of depreciable fixed assets in the previous year. DZCTis the original value of depreciable fixed assets. ΔDZCis the original value of newly added fixed assets.

3) The financing subsystem is shown in Eqs. 2123:

F=min(FBZ,FFZ)(21)
FBZ=(NpTp+D)×ε×(1λBZ)/λBZ(22)
FFZ=λFZ(FZCL+NpTpFHK)FFZL+FHK1λFZ(23)

In the formula, FBZand FFZare respectively the financing amount under the constraints of capital security rate and debt ratio. εis the cash flow coefficient; λBZis the capital security rate. λFZis the asset-liability ratio. FHKis the repayment amount. FZCLand FFZLare the assets and assets total liabilities.

5 Research on the calculation model of new power system load-side saving investment

Figure 7 shows the calculation process of the scale of investment savings on the load side in the coming years.

FIGURE 7
www.frontiersin.org

FIGURE 7. Flow chart of the scale of investment savings on the load side in the coming years.

The formula for calculating the scale of saving investment on the load side is shown in Eqs. 2425:

L=LxqLcb(24)
Lxq=Lgxq+Lzxq+Ldxq(25)

In the formula, Lxqis the saving investment on the demand side. Lcbis the cost of demand response. Lgxqis the high-voltage substation to save investment. Lzxqis the saving of investment in medium voltage equipment. Ldxqis for low-voltage equipment to save investment.

The cost of demand-side response (Yang et al., 2021) is calculated according to the regional demand response subsidy price scheme.

6 Research on investment calculation model of energy storage side of new power system

6.1 Energy storage side investment calculation model

Figure 8 shows the calculation process of the investment scale of the energy storage side in the future.

FIGURE 8
www.frontiersin.org

FIGURE 8. Calculation flow chart of investment scale of energy storage side in the future.

The total investment cost of the energy storage system is shown in Eqs. 2628:

W=W1+W2(26)
W1=WpsPEN+WesEN(27)
W2=WompPEN+WomeEN(28)

In the formula, W1is the initial energy storage system cost. W2is the operation and maintenance cost. Wpsis the unit energy storage power cost. PENis the energy storage rated power. Wesis the unit energy storage capacity cost. ENis the rated capacity of energy storage. Wompis the operation and maintenance cost of unit energy storage power. Womeis the operation and maintenance cost of unit energy storage capacity

6.2 Energy storage side investment income model

Figure 9 shows the calculation process of the investment income of the energy storage side in the future.

FIGURE 9
www.frontiersin.org

FIGURE 9. Flow chart of future annual investment income calculation of energy storage side.

The future annual investment income of the energy storage side is shown in Eq. 29:

I=Idw+Itl+Ibt(29)

1) Delaying investment in grid construction

The economic benefits of reducing investment in grid expansion and reconstruction by installing energy storage can avoid fixed capacity costs, which can be determined according to the average cost of substations, transformers, transmission lines, and their supporting equipment that are less or delayed in construction, as shown in Eq. 30:

Idw=AtφηPmax(30)

In the formula: Idwis the investment in grid construction that can be delayed. Atunit power cost of distribution network. φis the fixed asset depreciation rate of power distribution equipment. ηis the charge-discharge efficiency. Pmaxis the rated power of the energy storage.

2) Peak and valley arbitrage income

Under the premise of charging and discharging twice a day, the main benefits of user-side energy storage projects are the peak-valley price difference and the peak-to-parity price difference arbitrage.

Assuming two charges and two discharges per day, the peak electricity price under special circumstances is not considered, and only the peak, flat, and valley electricity prices are considered, and the daily charge and discharge income is calculated as shown in Eqs. 3133:

Itl=PfPc(31)
Pc=S(pm+pl)(32)
Pf=2Sηph(33)

In the formula: Itlis the peak-valley arbitrage income. Pfis the discharged income. Pcis the charging fee. Sis the rated capacity of energy storage on the user side. phis the peak electricity price. pmis the flat section electricity price. plis the low price of electricity. ηis the charge-discharge efficiency.

6.3 Policy subsidy income

Policy subsidy income Ibtis calculated according to the regional energy storage subsidy scheme.

6.4 Case analysis

6.4.1 Grid investment scale in historical years

The distribution network investment calculation method based on historical investment results (Li et al., 2019) and based on the new power system are respectively used to calculate the investment scale of the county’s power grid in the current year.

Based on the actual power grid investment scale from 2018 to 2021, the maximum deviation rate of the distribution network investment calculation method based on historical investment results is 9.42%, and the average deviation rate is 7.46%. But based on the new power system investment calculation, the maximum deviation rate is 4.14%, and the average deviation rate is 2.33%. The details are shown in Table 2.

TABLE 2
www.frontiersin.org

TABLE 2. Comparison of calculation results of two grid investment calculation methods.

The calculation results show that, compared with the distribution network investment calculation method based on historical investment results, the deviation rate of the distribution network investment calculation method based on the new power system is significantly smaller, and the investment scale is closer to the actual investment completion.

6.5 Grid investment scale in the coming years

Taking a county as a demonstration area, the investment scale of the county’s distribution network based on the new power system is predicted in 2022.

6.5.1 Investment calculation on the power supply side

The county is a Class C power supply area. In 2022, the installed capacity of distributed power supply in the county will reach 30 MVA, the current line can accommodate an installed capacity of 11.7 MVA, and the remaining capacity needs to be absorbed by new lines and distribution transformers. The variable side distributed installed capacity is 11.9 MV A. In 2022, the county’s power supply side investment is 3.6809 million dollars, and the details are shown in Table 3.

TABLE 3
www.frontiersin.org

TABLE 3. Calculation results of investment scale on the power supply side.

6.5.2 Grid side investment calculation

1) Calculation of power grid investment demand

In 2022, the county’s power grid investment demand is 18.3998 million dollars, and the specific results are shown in Table 4.

TABLE 4
www.frontiersin.org

TABLE 4. Calculated results of power grid investment demand scale.

Taking the highest electricity load of the whole society as an example, the sensitivity analysis of the index is carried out. In 2022, the highest electricity load in the whole society will increase by 8% compared with 2021. Assuming other conditions remain unchanged, a sensitivity analysis is carried out on the different growth rates of the highest electricity load in the whole society. The calculation results of the scale of power grid investment demand show that when the growth rate of the highest electricity load in the whole society changes between −20% and 20%, the predicted value of investment demand changes between −3.34% and 6.59%.

The changes in the forecast value of investment demand are shown in Table 5.

TABLE 5
www.frontiersin.org

TABLE 5. Sensitivity analysis results of the highest electricity load in the whole society.

After calculation, GDP, electricity sales, and the highest load of the whole society are the most sensitive factors.

2) Calculation of power grid investment capacity

Using the investment capacity prediction model, it is estimated that the county’s power grid investment capacity in 2022 will be 28.2955 million dollars. The specific results are shown in Table 6.

3) Calculation results of grid side investment

TABLE 6
www.frontiersin.org

TABLE 6. Calculation results of power grid investment capacity.

Taking into account the investment demand and investment capacity of the power grid in the region, the weights of the investment proportion calculated by the AHP method are 0.4 and 0.6 respectively, and considering the grid side investment correction coefficient of 0.95, the final investment on the grid side of the county in 2022 is 23.1204 million dollars.

6.6 Load-side saving investment calculation

In 2022, the maximum demand-side response load in the county is 30MW, and the demand-side load response coefficient is 0.7. Due to the interruptible load response, 30 km of new 10 kV overhead lines, 36 switches on the column, 7.2 km of overhead branch lines, 32 transformers on the column, and 32 km of overhead low-voltage lines can be reduced, saving investment of 3.5648 million dollars as shown in Table 7.

TABLE 7
www.frontiersin.org

TABLE 7. Save investment due to interruptible load response in 2022.

The annual fixed unit price of the electricity subsidy is 62.79 cents/kWh, the single response time is 2 h, and the number of responses in the whole year is 10 times. The demand response load in the county is 65,577kW, and the demand response cost is about 0.8231 million dollars.

To sum up, the load-side saving investment in 2022 is 2.7416 million dollars.

6.6.1 Energy storage side investment calculation

1) Investment scale of energy storage side

In this paper, the unit energy storage power cost is 0.3923 million dollars/MW, the unit energy storage capacity cost is 0.3138 million dollars/MWh, and the unit energy storage power operation and maintenance cost and unit energy storage capacity operation and maintenance cost are 6.276 dollars/kW. In 2022, the county’s energy storage side investment will be 4.6741 million dollars, the details are shown in Table 8.

2) Energy storage side investment income

TABLE 8
www.frontiersin.org

TABLE 8. Calculation results of investment scale on the energy storage side.

6.7 Delay grid construction

In this paper, the unit power cost of the distribution network is 0.1569 million dollars/MW, the charging and discharging efficiency is 81%, the fixed asset depreciation rate of the distribution equipment is 30%, and the rated power of the energy storage is 5 MW. According to Eq. 30, it can be obtained that the delay of power grid construction is 0.1906 million dollars.

6.8 Peak and valley arbitrage income

In this paper, the peak electricity price is 14.59 cents/kWh; the trough electricity price is 3.36 cents/kWh, and the flat segment electricity price is 8.34 dollars/kWh. The rated capacity of the user-side energy storage is 4 MWh, the charging and discharging efficiency is 81%, and the energy storage system works 330 days a year. Then the Eqs. 3133 can be obtained, the peak-valley arbitrage income is 0.1575 million dollars.

6.9 Energy storage subsidy income

The energy storage compensation standard in this area is 31.38 dollars/kW per year. After calculation, the energy storage subsidy income in this area is 0.1412 million dollars.

To sum up, in 2022, the energy storage side income in the region will be about 0.5678 million dollars, and the energy storage side investment in the region 2022 will be 4.1847 million dollars.

6.9.1 Calculation results of new power system investment in the demonstration area

The estimated scale of investment on the power supply side is 3.68 million dollars, the estimated scale of investment on the grid side is 23.1204 million dollars, the scale of saving investment on the load side is 2.7416 million dollars, and the estimated scale of investment on the energy storage side is 4.1847 million dollars.

According to the research idea of the new power system investment method, which can be obtained from Eq. 1, the total investment in the county’s new power system in 2022 is estimated to be 28.2443 million dollars.

7 Conclusion

Considering the investment and construction needs of new elements on the source, grid, load, and storage sides, this paper innovatively constructs an investment scale calculation model based on the new power system on the four sides of the source, grid, load, and storage. On the power supply side: Considering factors such as lines, distribution and transformation distributed power access standards, safe and reliable operation, and grid construction standards in different power supply areas, develop a new energy grid investment scale calculation model that takes into account safety and economy. On the grid side: overall consideration of regional investment needs and investment capacity, and research on the investment scale calculation model based on the three major financial statements, economic development and power demand. On the load side: Considering the interruptible load’s participation in peak shaving and the corresponding demand subsidy policy, a load-side saving investment scale calculation model that takes into account the benefits of the delay in the construction of the distribution network and the corresponding demand is developed. On the energy storage side: Considering the configuration of energy storage capacity and energy storage subsidy policy, develop an energy storage side investment calculation model that takes into account the costs and benefits of energy storage. The four-side investment calculation method based on the new power system, load and storage, plays an important role in meeting the precision requirements of distribution network investment projects under the new situation and improving the investment efficiency of the power grid.

The research results are applied to the calculation of the investment scale of a new power system in a county in the future, and can accurately predict the investment scale of the next year. From the perspective of historical years, compared with the traditional distribution network investment calculation method, the calculation results of the four-side investment scale calculation method of the source network, load and storage are more accurate and have certain forward-looking results. In the future, the input data optimization model can be revised based on accumulated experience, providing more flexible investment plans for long-term construction investment decisions, continuously improving the accuracy of model prediction, and better adapting to the new energy-based distribution network under the “carbon peaking and carbon neutrality” goals. New power system planning investment decisions.

Data availability statement

The original contributions presented in the study are included in the article/supplementary material, further inquiries can be directed to the corresponding author.

Author contributions

ZF was responsible for the specific work of this article. ZF and XL guided the work of this article. CD and FJ did some calculations. FJ and WJ collected data and calculated and compared the plans.

Funding

The authors acknowledge the funding of the State Grid Corporation of China’s Science and Technology Project (JSB17202000260).

Acknowledgments

The corresponding author thanks State Grid Jiaxing Electric Power Supply Company and State Grid Zhejiang Electric Power Co., Ltd. Pinghu Power Supply Company’s selfless support.

Conflict of interest

The authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Publisher’s note

All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article, or claim that may be made by its manufacturer, is not guaranteed or endorsed by the publisher.

References

Abdelkader, A., Rabeh, A., Ali, D. M., and Mohamed, J. (2018). Multi-objective genetic algorithm based sizing optimization of a stand-alone wind/PV power supply system with enhanced battery/supercapacitor hybrid energy storage. Energy 163, 351–363. doi:10.1016/j.energy.2018.08.135

CrossRef Full Text | Google Scholar

Elkadeem, M. R., Abd Elaziz, M., Ullah, Z., Wang, S., and Sharshir, S. W. (2019). Optimal planning of renewable energy-integrated distribution system considering uncertainties. IEEE Access 7, 164887–164907. doi:10.1109/ACCESS.2019.2947308

CrossRef Full Text | Google Scholar

Gao, J., Wu, F., Yasen, Y., Song, W., and Ren, L. (2022). Generalized Cauchy process based on heavy-tailed distribution and grey relational analysis for reliability predicting of distribution systems. Math. Biosci. Eng. 19 (7), 6620–6637. doi:10.3934/mbe.2022311

PubMed Abstract | CrossRef Full Text | Google Scholar

Gao, L., and Zhao, Z. Y. (2018). System dynamics analysis of evolutionary game strategies between the government and investors based on new energy power construction public-private-partnership (PPP) project. Sustainability 10 (7), 2533. doi:10.3390/su10072533

CrossRef Full Text | Google Scholar

He, Y., Xiong, W., Yang, B., Yang, H. Y., Zhou, J. F., Cui, M. L., et al. (2022). Combined game model and investment decision making of power grid-distributed energy system. Environ. Dev. Sustain. 24 (6), 8667–8690. doi:10.1007/s10668-021-01804-3

CrossRef Full Text | Google Scholar

Li, K., Fu, G. H., and Tian, C. S. (2019). Distribution network investment allocation and project opimization method considering the historical investment effectiveness. Comput. Technol. Automation 38, 33–38. doi:10.16339/j.cnki.jsjsyzdh.201903007

CrossRef Full Text | Google Scholar

Luo, C., Ling, W., Mo, D., Li, Y., Li, Q., Liang, Z., et al. (2021). Power system load forecasting method based on LSTM network. J. Phys. Conf. Ser. 2005, 012179. doi:10.1088/1742-6596/2005/1/012179

CrossRef Full Text | Google Scholar

Nazir, M. S., Abdalla, A. N., Sohail, H. M., Tang, Y., Rashed, G. I., and Chen, W. (2021). Optimal planning and investment of Multi-renewable power generation and energy storage system capacity. J. Electr. Syst. 17 (2), 171–181. doi:10.1016/j.est.2020.101866

CrossRef Full Text | Google Scholar

Ren, X., Ye, B., Yang, N., Shao, H., and Gao, C. (2019). “Investment optimization of incremental distribution network based on cooperative game in the context of investment liberalization,” in 2019 IEEE innovative smart grid technologies-asia (ISGT asia) (IEEE), 888–893. doi:10.1109/ISGT-Asia.2019.8881271

CrossRef Full Text | Google Scholar

Sánchez, A., Zhang, Q., Martín, M., and Vega, P. (2022). Towards a new renewable power system using energy storage: An economic and social analysis. Energy Convers. Manag. 252, 115056. doi:10.1016/j.enconman.2021.115056

CrossRef Full Text | Google Scholar

Wang, X., Zhou, Z., Sun, L., Xie, G., and Lou, Q. (2021). Study on the whole process evaluation of new energy grid connection based on AHP-entropy weight method IOP conference series: Earth and environmental science. IOP Conf. Ser. Earth Environ. Sci. 831 (1), 012023. doi:10.1088/1755-1315/831/1/012023

CrossRef Full Text | Google Scholar

Wu, W., Li, M., Yan, T., Huang, P., Lu, X., and Wang, Z. (2019). “Distribution network project portfolio optimization decision model based on power demand matching,” in 2019 IEEE PES asia-pacific power and energy engineering conference (Macau, China: APPEEC), 1–5. doi:10.1109/APPEEC45492.2019.8994475

CrossRef Full Text | Google Scholar

Yang, H., Wang, L., Ma, Y., Zhang, D., and Wu, H. (2021). Optimization strategy of price-based demand response considering the bidirectional feedback effect. IET Gener. Transm. Distrib. 15 (11), 1752–1762. doi:10.1049/gtd2.12131

CrossRef Full Text | Google Scholar

Yi, L., Li, T., and Zhang, T. (2021). Optimal investment selection of regional integrated energy system under multiple strategic objectives portfolio. Energy 218, 119409. doi:10.1016/j.energy.2020.119409

CrossRef Full Text | Google Scholar

Zhang, M., Tang, Y., Liu, L., and Zhou, D. (2022). Optimal investment portfolio strategies for power enterprises under multi-policy scenarios of renewable energy. Renew. Sustain. Energy Rev. 154, 111879. doi:10.1016/j.rser.2021.111879

CrossRef Full Text | Google Scholar

Zheng, Y., Li, J., and Jiao, Y. (2021). “Distribution network planning and comprehensive investment evaluation based on bayes-entropy weight-fuzzy analytic hierarchy process,” in 2021 IEEE international conference on power electronics (Shenyang, China: Computer Applications (ICPECA), 477–481. doi:10.1109/ICPECA51329.2021.9362726

CrossRef Full Text | Google Scholar

Zhu, M., Xie, Z., and Wang, Z. (2022). “Digital transformation and development of provincial power grid enterprises,” in 2021 international conference on smart technologies and systems for Internet of things (STS-IOT 2021) (Shanghai, China: Atlantis Press), 16–20. doi:10.2991/ahis.k.220601.004

CrossRef Full Text | Google Scholar

Keywords: new power system, distribution network investment, source network load-storage, calculation model, precise investment

Citation: Fei Z, Longjiang X, Jingliang Z, Ding C, Jinghui F and Jun W (2023) A novel investment strategy for renewable-dominated power distribution networks. Front. Energy Res. 10:968944. doi: 10.3389/fenrg.2022.968944

Received: 14 June 2022; Accepted: 31 August 2022;
Published: 05 January 2023.

Edited by:

Bin Zhou, Hunan University, China

Reviewed by:

Leijiao Ge, Tianjin University, China
Diansheng LUO, Hunan University, China
Yibo Wang, Northeast Dianli University, China

Copyright © 2023 Fei, Longjiang, Jingliang, Ding, Jinghui and Jun. This is an open-access article distributed under the terms of the Creative Commons Attribution License (CC BY). The use, distribution or reproduction in other forums is permitted, provided the original author(s) and the copyright owner(s) are credited and that the original publication in this journal is cited, in accordance with accepted academic practice. No use, distribution or reproduction is permitted which does not comply with these terms.

*Correspondence: Zhao Fei, emZqeGRsQDEyNi5jb20=

Disclaimer: All claims expressed in this article are solely those of the authors and do not necessarily represent those of their affiliated organizations, or those of the publisher, the editors and the reviewers. Any product that may be evaluated in this article or claim that may be made by its manufacturer is not guaranteed or endorsed by the publisher.